3081UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09% 09/10/2024
3082UKL/DAR/2022-23/Rd2/09 CRIF-Ngaimu-Tuinem16kmImpvt. of Road from Ngaimu/Tolloi Junction to Tuinem 16 KmPWDUkhrulPhase 178.09%09/10/2024
3083UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 1100% completed09/10/2024
3084UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3085UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3086UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3087UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3088UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3089UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3090UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 1100% completed 09/10/2024
3091UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3092UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3093UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3094UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3095UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3096UKL/Khamasom Khullen to KhamasomPhungdhar/239Construction of Blacktopping from Khamasom Khullen to Khamasom Phungdhar villagePWDUkhrulPhase 180% progress09/10/2024
3097UKL/DAR/2022-23/Rd1/318-15Improvement of IVR from Wallely to Sihai Khunou VillagePWDUkhrulPhase 1100% completed 09/10/2024
3098UKL/DAR/2022-23/Rd1/318-15Improvement of IVR from Wallely to Sihai Khunou VillagePWDUkhrulPhase 1100% completed 09/10/2024
3099UKL/DAR/2022-23/Rd1/318-15Improvement of IVR from Wallely to Sihai Khunou VillagePWDUkhrulPhase 1100% completed 09/10/2024
3100SS/21-DI/AthokpamMakhaUPS/ThoubalStrengthening of School under Samagra Shiksha for the year 2019-20 of Athokpam Makha UPS, Thoubal Education (S)Thoubalnilinprogess 09/10/2024