2981 | TPL/Kangoi Khuningsi to Water Supply/207 | Constn of road from Kangoi Khuningsi to Water Supply | PWD | Tengnoupal | 1 | 90% | 20/09/2024 |
2982 | TPL/Kangoi Khuningsi to Water Supply/207 | Constn of road from Kangoi Khuningsi to Water Supply | PWD | Tengnoupal | 1 | 90% | 20/09/2024 |
2983 | TPL/Kangoi Khuningsi to Water Supply/207 | Constn of road from Kangoi Khuningsi to Water Supply | PWD | Tengnoupal | 1 | 90% | 20/09/2024 |
2984 | NNY/Nungnang Gairilong Village to Tanlok/223 | Impvt of IVR from Nungnang Gairilong Village To Tanlok Village | PWD | Noney | 2nd and final phase | 100 | 20/09/2024 |
2985 | NNY/Nungnang Gairilong Village to Tanlok/223 | Impvt of IVR from Nungnang Gairilong Village To Tanlok Village | PWD | Noney | 2nd and final phase | 100 | 20/09/2024 |
2986 | SDH/DAR/2022-23/R2/328-10 Mission Road | Impvt. of Mission road to Hydro Colony, Kangpokpi via Hangmi Veng | PWD | Kangpokpi | phase-I | 100% works completed | 20/09/2024 |
2987 | SDH/DAR/2022-23/R2/328-10 Mission Road | Impvt. of Mission road to Hydro Colony, Kangpokpi via Hangmi Veng | PWD | Kangpokpi | phase-I | 100% works completed | 20/09/2024 |
2988 | SDH/DAR/2022-23/R2/328-10 Mission Road | Impvt. of Mission road to Hydro Colony, Kangpokpi via Hangmi Veng | PWD | Kangpokpi | phase-I | 100% works completed | 20/09/2024 |
2989 | Ukl/2022/Eastern-Western circular road/RIDF/1 | Impvt. of Eastern and Western circular road in Ukhrul | PWD | Ukhrul | Phase 1 | 100% | 19/09/2024 |
2990 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2991 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2992 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2993 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2994 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2995 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2996 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
2997 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | in progress | 19/09/2024 |
2998 | BRD/RCC Bridge-Kamong Meisnam/35 | Constn. of RCC Bridge over Leimakhong River at Kamong Meisnam Leikai | PWD | Imphal-West | --- | completed | 19/09/2024 |
2999 | TML/Noney-Marangching/6 | Impvt. of Noney-Marangching (Railway Project road) (SH: Shingling 8.20 Km WBM Gr-II 8.20 Km and constn. of 900 mm dia RCC pipe culvert NP3 7.50 Rm ... | PWD | Tamenglong | 3rd | completed | 19/09/2024 |
3000 | TML/Noney-Marangching/6 | Impvt. of Noney-Marangching (Railway Project road) (SH: Shingling 8.20 Km WBM Gr-II 8.20 Km and constn. of 900 mm dia RCC pipe culvert NP3 7.50 Rm ... | PWD | Tamenglong | 3rd | completed | 19/09/2024 |