Project Updates
Showing 241-260 of 30,825 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
241JBM/Renovation-EE Bunglow/33Renovation of EE PWD Banglow including protection of Compound wall at JiribamPWDJiribamphase1completed29/01/2026
242SPT/paverblocks of TNK road Senapati/351construction of rigid pavement with interlocking paver blocks in Senapati District HQ Rd SH Const of rigid pavement of TNK roadPWDSenapati1In progress 29/01/2026
243SPT/paverblocks of TNK road Senapati/351construction of rigid pavement with interlocking paver blocks in Senapati District HQ Rd SH Const of rigid pavement of TNK roadPWDSenapati1In progress 29/01/2026
244SPT/paverblocks Katomei road/349construction of rigid pavement with interlocking paver blocks in Senapati District HQ Rd SH Const of rigid pavement of Katomei roadPWDSenapati1In progress 29/01/2026
245SPT/paverblocks Katomei road/349construction of rigid pavement with interlocking paver blocks in Senapati District HQ Rd SH Const of rigid pavement of Katomei roadPWDSenapati1In progress 29/01/2026
246SPT/paver block of SPT Old road/340construction of pavement with interlocking paver blocks in SPT District HQ Rd SH Construction of rigid pavement of Senapati Old roadPWDSenapati1In progress29/01/2026
247SPT/paver block of SPT Old road/340construction of pavement with interlocking paver blocks in SPT District HQ Rd SH Construction of rigid pavement of Senapati Old roadPWDSenapati1In progress 29/01/2026
248SPT/paver block of SPT Old road/340construction of pavement with interlocking paver blocks in SPT District HQ Rd SH Construction of rigid pavement of Senapati Old roadPWDSenapati1In progress 29/01/2026
249CCP/Rigid pavmt Mary Kom Ringrd/330construction of rigid pavement with thin white topping in Churachandpur District HQ Rd SH May Kom Ring roadPWDChurachandpur2024-2535% complete29/01/2026
250CCP/Rigid pavmt Mary Kom Ringrd/330construction of rigid pavement with thin white topping in Churachandpur District HQ Rd SH May Kom Ring roadPWDChurachandpur2024-2535% complete29/01/2026
251CCP/Rigid pavmt Mary Kom Ringrd/330construction of rigid pavement with thin white topping in Churachandpur District HQ Rd SH May Kom Ring roadPWDChurachandpur2024-2535% complete29/01/2026
252NEC/16-RDHS-GH-IEConstruction Girls Hostel at Raja Dumbra High School Campus, Imphal East, Manipur.Education (S)Imphal-EastNillCompleted28/01/2026
253NEC/16-RDHS-GH-IEConstruction Girls Hostel at Raja Dumbra High School Campus, Imphal East, Manipur.Education (S)Imphal-EastNillCompleted28/01/2026
254NEC/16-RDHS-GH-IEConstruction Girls Hostel at Raja Dumbra High School Campus, Imphal East, Manipur.Education (S)Imphal-EastNillCompleted28/01/2026
255NEC/16-RDHS-GH-IEConstruction Girls Hostel at Raja Dumbra High School Campus, Imphal East, Manipur.Education (S)Imphal-EastNillCompleted28/01/2026
256NEC/16-RDHS-GH-IEConstruction Girls Hostel at Raja Dumbra High School Campus, Imphal East, Manipur.Education (S)Imphal-EastNillUnder Construction28/01/2026
257NEC/16-RDHS-GH-IEConstruction Girls Hostel at Raja Dumbra High School Campus, Imphal East, Manipur.Education (S)Imphal-EastNillCompleted28/01/2026
258SS/D-2/ LangthabalKhunouPS 5ACR-TBLConstruction of Dilapidated Building Primary School Under Samagra Shiksha (Elementary) Manipur during 2022-2023 at Langthabal Khunou Primary School, TEducation (S)ThoubalnilCompleted28/01/2026
259SS/D-2/ LangthabalKhunouPS 5ACR-TBLConstruction of Dilapidated Building Primary School Under Samagra Shiksha (Elementary) Manipur during 2022-2023 at Langthabal Khunou Primary School, TEducation (S)ThoubalNillCompleted 28/01/2026
260SS/D-2/ LangthabalKhunouPS 5ACR-TBLConstruction of Dilapidated Building Primary School Under Samagra Shiksha (Elementary) Manipur during 2022-2023 at Langthabal Khunou Primary School, TEducation (S)ThoubalnilCompleted28/01/2026