#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
201PZL/JT Road-Phailen/8M/o of road fro JT road to Phailen via Tuisen - 5kmPWDPherzawl2020-21100% works completed 30/01/2026
202PZL/JT Road-Phailen/8M/o of road fro JT road to Phailen via Tuisen - 5kmPWDPherzawl2020-21The work has been completed upto 85 Percentage30/01/2026
203TML/New&Old DC Bungalow-TML/87Renovation and Improvement of New & Old DC Bungalow at Tamenglong HQPWDTamenglong1in progress30/01/2026
204TML/New&Old DC Bungalow-TML/87Renovation and Improvement of New & Old DC Bungalow at Tamenglong HQPWDTamenglong1in progress30/01/2026
205TML/New&Old DC Bungalow-TML/87Renovation and Improvement of New & Old DC Bungalow at Tamenglong HQPWDTamenglong1in progress30/01/2026
206TML/New&Old DC Bungalow-TML/87Renovation and Improvement of New & Old DC Bungalow at Tamenglong HQPWDTamenglong1in progress30/01/2026
207SPT/Paver block of Dist Hospital road/339construction of pavement with interlocking paver blocks in SPT District HQ Rd SH Construction of rigid pavement of Senapati District Hospital roadPWDSenapati1In progress 30/01/2026
208SPT/Paver block of Dist Hospital road/339construction of pavement with interlocking paver blocks in SPT District HQ Rd SH Construction of rigid pavement of Senapati District Hospital roadPWDSenapati1In progress 30/01/2026
209SPT/Paver block of Dist Hospital road/339construction of pavement with interlocking paver blocks in SPT District HQ Rd SH Construction of rigid pavement of Senapati District Hospital roadPWDSenapati1In progress 30/01/2026
210ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney2nd phase100%30/01/2026
211ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney2nd phase100%30/01/2026
212ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
213ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
214ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase10030/01/2026
215ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
216ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
217ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
218ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
219ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026
220ND/Road/Nungba/11Black topping of ODR from Nungba Bazar to Nungba New SDO Office 3.00km.PWDNoney3rd Phase100%30/01/2026