7061BD-II/AE-III/MLA Flat/2019-20Renovation of MLA Flat at Babupara.PWDImphal-East58.250.00Others17/03/20202019-2020Project Status
7062IED/Slab culvert-Line drain/397Constn. of Slab culvert 5m span RCC culvert, Chana, 5m span at Lamlai Karthong, 4m span at Lamlai Maning Leikai, 5m span at Sheijang Teramakhong .....PWDImphal-East200.000State Plan16/03/20202016-2017Project Status
7063IED/Kshetrigao/Idigah/396M/o road from Kshetrigao/Idigah road to Top Western side of Iril riverPWDImphal-East19.978.00State Plan16/03/20202017-2018Project Status
706462/9/2018/SPP/DC/MANIREDA(IE)Conversion of Off grid to Grid Interactive SPV Power Plant,Imphal EastMANIREDAImphal-East82.440State Plan16/03/20202019-2020Project Status
7065TML/Eleng-Chaton/44Improvement of road from Eleng to Chaton - 7 kmPWDTamenglong29.960.00State Plan16/03/20202018-2019Project Status
7066MANIDCO_C&I_31CONSTRUCTION OF COMPOUND FENCING OF DIC/ACTC (WESTERN & SOUTHERN SIDE), POROMPAT, DIC, IMPHAL EASTCommerce and IndustriesImphal-East59.970State Plan16/03/20202019-2020Project Status
7067TML/Thiulon-Vachengphai/43Impvt. of road from Thiulon to Vachengphai IVRPWDTamenglong29.980.00State Plan16/03/20202018-2019Project Status
7068TML/Old-New Lenglong/42Impvt. of road from Old Lenglong to New Lenglong IVRPWDTamenglong29.930.00State Plan16/03/20202018-2019Project Status
7069TML/Ndetning-Kuiling/41Impvt. of road from Ndetning to Kuilong-II IVRPWDTamenglong29.940.00State Plan16/03/20202018-2019Project Status
7070TML/Ningdi-Chrinapeng/40Improvement of road from Ningdi to ChrinapengPWDTamenglong29.990.00State Plan16/03/20202018-2019Project Status
7071IWD/Thingom-Khwai Ningthou/148M/o road Thingom Leikai and Khwai Ningthou LeikaiPWDImphal-West35.0024State Plan16/03/20202018-2019Project Status
7072IWD/Pukhrambam Thangjam Leirak/147M/o roads Pukrambam Leirak, Thangjam LeirakPWDImphal-West15.0011State Plan16/03/20202019-2020Project Status
7073IWD/North Kangla Gate/149Restoration of Norther Kangla gate to KhuyathongPWDImphal-West20.000State Plan16/03/20202018-2019Project Status
7074IWD/Nambulan Jail/146M/o of Nambulan Jail road internal roadPWDImphal-West16.0010State Plan16/03/20202019-2020Project Status
7075IWD/Mantri Leikai/145M/o of road Mantri Leikai Maning LeirakPWDImphal-West20.000.00State Plan16/03/20202018-2019Project Status
7076IWD/Takelambam Leikai/144M/o of road Takhelambam Leikai internal roadsPWDImphal-West19.100.00State Plan16/03/20202018-2019Project Status
7077IWD/Bijoygobinda Internal/143M/o of Bijoygovinda Internal roadPWDImphal-West20.0012State Plan16/03/20202018-2019Project Status
7078IWD/Mayaikoibi Thounaojam/142M/o Road Mayaikoibi Thounaojam LeirakPWDImphal-West74.0050State Plan16/03/20202018-2019Project Status
707919/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang)LED SOlar street light in MoirangMANIREDABishnupur127.130State Plan16/03/20202019-2020Project Status
708019/41/2018/MNRE(SSL/LMP)/MANIKREDA(CCpur)LED Solar Street lightMANIREDAChurachandpur127.130State Plan16/03/20202019-2020Project Status