18661EVMJBMConstruction of ERO/DC EVMs Strong room at JiribamManipur Police Housing Corporation Ltd.JiribamPhase I65% Completed01/02/2021
18662EVM-SPTConstruction of Senapati DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.SenapatiSingle35 percent completed01/02/2021
18663EVM-SPTConstruction of Senapati DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.SenapatiSingle35 percent completed01/02/2021
18664EVM-SPTConstruction of Senapati DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.SenapatiSingle30 percent completed01/02/2021
18665EVM-KPIConstruction of Kangpokpi DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.KangpokpiSingle45 percent completed01/02/2021
18666EVM-KPIConstruction of Kangpokpi DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.KangpokpiSingle45 percent completed01/02/2021
18667EVM-KPIConstruction of Kangpokpi DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.KangpokpiSingle45 percent completed01/02/2021
18668EVMCCPConstruction of Churachandpur DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.ChurachandpurSingle40 percent completed01/02/2021
18669EVMCCPConstruction of Churachandpur DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.ChurachandpurSingle40 percent completed01/02/2021
18670EVMCCPConstruction of Churachandpur DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.ChurachandpurSingle40 percent completed01/02/2021
18671EVMBPRConstruction of Bishnupur DEO/DC EVMs Strong room.Manipur Police Housing Corporation Ltd.BishnupurSingle20PC01/02/2021
18672EVMBPRConstruction of Bishnupur DEO/DC EVMs Strong room.Manipur Police Housing Corporation Ltd.BishnupurSingle20 percent completed01/02/2021
18673IED/Andro Kharam IVR/549Impvt. of road from Andro Kharam Leikai IVR road 2.50 kmPWDImphal-East1In progress01/02/2021
18674JBM/Compound Fencing-Guest House/12Constn. of compound fencing (left out portion) for Guest House at Jiribam i/c approach roadPWDJiribamPhase-IICompleted01/02/2021
18675EVMIWConstruction of Imphal West DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.Imphal-WestSingle3o% completed01/02/2021
18676EVMIWConstruction of Imphal West DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.Imphal-WestSingle3o% completed01/02/2021
18677EVMIWConstruction of Imphal West DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.Imphal-WestSingle30% Completed.01/02/2021
18678EVMCEOConstruction of CEO's Office EVMs Strong Room, Lamphelpat.Manipur Police Housing Corporation Ltd.Imphal-WestSingleCasting of Roof slab Completed.01/02/2021
18679EVMCEOConstruction of CEO's Office EVMs Strong Room, Lamphelpat.Manipur Police Housing Corporation Ltd.Imphal-WestSingleCasting of Roof slab completed.01/02/2021
18680EVMIEConstruction of Imphal East DEO/DC EVMs Strong Room,Porompat.Manipur Police Housing Corporation Ltd.Imphal-EastSingleOut of 66 pile 35 pile casting completed01/02/2021