| 18301 | CSCBPR Nungoo Pombikhok | Construction of CSC at Nungoo Pombikhok | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 18302 | CSCBPR Sagolpat | Construction of CSC at Sagolpat | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 18303 | CSC BPR Wangoo Laikhong | Construction of CSC at Wangoo Laikhong | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 18304 | CSC BPR Khordak | Construction of Community Sanitary complex at Khordak | PHED | Bishnupur | I | completed | 08/12/2020 |
| 18305 | CSC BPR Nongmaikhong | Construction of Community Sanitary complex at Nongmaikhong | PHED | Bishnupur | I | Completed | 08/12/2020 |
| 18306 | CSC BPR Moirang Khunou | Construction of Community Sanitary complex at Moirang Khunou | PHED | Bishnupur | I | Completed | 08/12/2020 |
| 18307 | CSC BPR Thangalawai | Construction of Community Sanitary complex at Thangalawai | PHED | Bishnupur | I | Completed | 08/12/2020 |
| 18308 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18309 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18310 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18311 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18312 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18313 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18314 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18315 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 18316 | DC/DRDA(IE)/9/Huikap Hostel | Construction of 100 bedded Girls Hostel at Huikap High School. | MOBC | Imphal-East | Phase-Ii | Ongoing | 08/12/2020 |
| 18317 | DC/DRDA/IE/11/Huikap High Schhol | Construction 10 ACRs at Huikap High School | MOBC | Imphal-East | Phase-Ii | Ongoing | 08/12/2020 |
| 18318 | DC/DRDA/IE/15/KGBV(NP)/School, Andro | Upgradation of KGBV Andro NP (8 rooms) | MOBC | Imphal-East | Phase-Ii | Ongoing | 08/12/2020 |
| 18319 | DC/DRDA/IE/14/Hostel/KGBV/Andro | Construction of 100 bedded Hostel at KGBV (NP)at Andro | MOBC | Imphal-East | Phase-Ii | Ongoing | 08/12/2020 |
| 18320 | DC/DRDA/IE/12/Ramanda High School | Construction of 10 ACRs of Ramananda High School | MOBC | Imphal-East | Phase -Ii | Ongoing | 08/12/2020 |