Project Updates
Showing 17,821-17,840 of 30,032 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
17821EVMCCPConstruction of Churachandpur DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.ChurachandpurSingle40 percent completed01/02/2021
17822EVMCCPConstruction of Churachandpur DEO/DC EVMs Strong RoomManipur Police Housing Corporation Ltd.ChurachandpurSingle40 percent completed01/02/2021
17823EVMBPRConstruction of Bishnupur DEO/DC EVMs Strong room.Manipur Police Housing Corporation Ltd.BishnupurSingle20PC01/02/2021
17824EVMBPRConstruction of Bishnupur DEO/DC EVMs Strong room.Manipur Police Housing Corporation Ltd.BishnupurSingle20 percent completed01/02/2021
17825IED/Andro Kharam IVR/549Impvt. of road from Andro Kharam Leikai IVR road 2.50 kmPWDImphal-East1In progress01/02/2021
17826JBM/Compound Fencing-Guest House/12Constn. of compound fencing (left out portion) for Guest House at Jiribam i/c approach roadPWDJiribamPhase-IICompleted01/02/2021
17827EVMIWConstruction of Imphal West DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.Imphal-WestSingle3o% completed01/02/2021
17828EVMIWConstruction of Imphal West DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.Imphal-WestSingle3o% completed01/02/2021
17829EVMIWConstruction of Imphal West DEO/DC EVMs Strong Room.Manipur Police Housing Corporation Ltd.Imphal-WestSingle30% Completed.01/02/2021
17830EVMCEOConstruction of CEO's Office EVMs Strong Room, Lamphelpat.Manipur Police Housing Corporation Ltd.Imphal-WestSingleCasting of Roof slab Completed.01/02/2021
17831EVMCEOConstruction of CEO's Office EVMs Strong Room, Lamphelpat.Manipur Police Housing Corporation Ltd.Imphal-WestSingleCasting of Roof slab completed.01/02/2021
17832EVMIEConstruction of Imphal East DEO/DC EVMs Strong Room,Porompat.Manipur Police Housing Corporation Ltd.Imphal-EastSingleOut of 66 pile 35 pile casting completed01/02/2021
17833EVMIEConstruction of Imphal East DEO/DC EVMs Strong Room,Porompat.Manipur Police Housing Corporation Ltd.Imphal-EastSingleOut of 66 pile 35 pile casting completed01/02/2021
17834EVMIEConstruction of Imphal East DEO/DC EVMs Strong Room,Porompat.Manipur Police Housing Corporation Ltd.Imphal-EastSinglePile work in foundation in progress01/02/2021
17835RIDF_PHED"Re-construction of Water supply System for providing water to the outskirts of Imphal and enroute villages under RIDF" PHEDImphal-EastPhase 1Ongoing01/02/2021
17836RIDF_PHED"Re-construction of Water supply System for providing water to the outskirts of Imphal and enroute villages under RIDF" PHEDImphal-EastPhase 1Ongoing01/02/2021
17837RIDF_PHED"Re-construction of Water supply System for providing water to the outskirts of Imphal and enroute villages under RIDF" PHEDImphal-EastPhase 1Ongoing01/02/2021
17838RIDF_PHED"Re-construction of Water supply System for providing water to the outskirts of Imphal and enroute villages under RIDF" PHEDImphal-EastPhase 1Ongoing01/02/2021
17839RIDF_PHED"Re-construction of Water supply System for providing water to the outskirts of Imphal and enroute villages under RIDF" PHEDImphal-EastPhase 1Ongoing01/02/2021
17840RIDF_PHED"Re-construction of Water supply System for providing water to the outskirts of Imphal and enroute villages under RIDF" PHEDImphal-EastPhase 1Ongoing01/02/2021