16641 | EVMJBM | Construction of ERO/DC EVMs Strong room at Jiribam | Manipur Police Housing Corporation Ltd. | Jiribam | Phase I | 65% Completed | 01/02/2021 |
16642 | EVMJBM | Construction of ERO/DC EVMs Strong room at Jiribam | Manipur Police Housing Corporation Ltd. | Jiribam | Phase I | 65% Completed | 01/02/2021 |
16643 | EVMJBM | Construction of ERO/DC EVMs Strong room at Jiribam | Manipur Police Housing Corporation Ltd. | Jiribam | Phase I | 65% Completed | 01/02/2021 |
16644 | EVM-SPT | Construction of Senapati DEO/DC EVMs Strong Room. | Manipur Police Housing Corporation Ltd. | Senapati | Single | 35 percent completed | 01/02/2021 |
16645 | EVM-SPT | Construction of Senapati DEO/DC EVMs Strong Room. | Manipur Police Housing Corporation Ltd. | Senapati | Single | 35 percent completed | 01/02/2021 |
16646 | EVM-SPT | Construction of Senapati DEO/DC EVMs Strong Room. | Manipur Police Housing Corporation Ltd. | Senapati | Single | 30 percent completed | 01/02/2021 |
16647 | EVM-KPI | Construction of Kangpokpi DEO/DC EVMs Strong Room | Manipur Police Housing Corporation Ltd. | Kangpokpi | Single | 45 percent completed | 01/02/2021 |
16648 | EVM-KPI | Construction of Kangpokpi DEO/DC EVMs Strong Room | Manipur Police Housing Corporation Ltd. | Kangpokpi | Single | 45 percent completed | 01/02/2021 |
16649 | EVM-KPI | Construction of Kangpokpi DEO/DC EVMs Strong Room | Manipur Police Housing Corporation Ltd. | Kangpokpi | Single | 45 percent completed | 01/02/2021 |
16650 | EVMCCP | Construction of Churachandpur DEO/DC EVMs Strong Room | Manipur Police Housing Corporation Ltd. | Churachandpur | Single | 40 percent completed | 01/02/2021 |
16651 | EVMCCP | Construction of Churachandpur DEO/DC EVMs Strong Room | Manipur Police Housing Corporation Ltd. | Churachandpur | Single | 40 percent completed | 01/02/2021 |
16652 | EVMCCP | Construction of Churachandpur DEO/DC EVMs Strong Room | Manipur Police Housing Corporation Ltd. | Churachandpur | Single | 40 percent completed | 01/02/2021 |
16653 | EVMBPR | Construction of Bishnupur DEO/DC EVMs Strong room. | Manipur Police Housing Corporation Ltd. | Bishnupur | Single | 20PC | 01/02/2021 |
16654 | EVMBPR | Construction of Bishnupur DEO/DC EVMs Strong room. | Manipur Police Housing Corporation Ltd. | Bishnupur | Single | 20 percent completed | 01/02/2021 |
16655 | IED/Andro Kharam IVR/549 | Impvt. of road from Andro Kharam Leikai IVR road 2.50 km | PWD | Imphal-East | 1 | In progress | 01/02/2021 |
16656 | JBM/Compound Fencing-Guest House/12 | Constn. of compound fencing (left out portion) for Guest House at Jiribam i/c approach road | PWD | Jiribam | Phase-II | Completed | 01/02/2021 |
16657 | EVMIW | Construction of Imphal West DEO/DC EVMs Strong Room. | Manipur Police Housing Corporation Ltd. | Imphal-West | Single | 3o% completed | 01/02/2021 |
16658 | EVMIW | Construction of Imphal West DEO/DC EVMs Strong Room. | Manipur Police Housing Corporation Ltd. | Imphal-West | Single | 3o% completed | 01/02/2021 |
16659 | EVMIW | Construction of Imphal West DEO/DC EVMs Strong Room. | Manipur Police Housing Corporation Ltd. | Imphal-West | Single | 30% Completed. | 01/02/2021 |
16660 | EVMCEO | Construction of CEO's Office EVMs Strong Room, Lamphelpat. | Manipur Police Housing Corporation Ltd. | Imphal-West | Single | Casting of Roof slab Completed. | 01/02/2021 |