16121 | WRD-FCW-144 | Post Monsoon Works(SH - Improvement of ebankment along RBB of Thoubal River from Khekman RCC bridge to Amakcham) | Water Resources Department (WRD) | Thoubal | last | complete | 01/03/2021 |
16122 | WRD-FCW-144 | Post Monsoon Works(SH - Improvement of ebankment along RBB of Thoubal River from Khekman RCC bridge to Amakcham) | Water Resources Department (WRD) | Thoubal | last | complete | 01/03/2021 |
16123 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th RCE | On going | 01/03/2021 |
16124 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th RCE | On going | 01/03/2021 |
16125 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th RCE | On going | 01/03/2021 |
16126 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th RCE | On going | 01/03/2021 |
16127 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6 revised | Ongoing | 01/03/2021 |
16128 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6 | Ongoing | 01/03/2021 |
16129 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th Revised | Ongoing | 01/03/2021 |
16130 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th Revised | Ongoing | 01/03/2021 |
16131 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th Revised | Ongoing | 01/03/2021 |
16132 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6 revised | Ongoing | 01/03/2021 |
16133 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | On going 6th revised | Completed | 01/03/2021 |
16134 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | On going 6th revised | Completed | 01/03/2021 |
16135 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | On going 6th revised | Completed | 01/03/2021 |
16136 | UKL/Kuingai/69 | Improvement of road from Kuingai to Tusom (SH:-Earth work, shingling and side drainage)- 10km | PWD | Ukhrul | 1 | Ongoing 45% | 01/03/2021 |
16137 | UKL/Kuingai/69 | Improvement of road from Kuingai to Tusom (SH:-Earth work, shingling and side drainage)- 10km | PWD | Ukhrul | 1 | Ongoing 45% | 01/03/2021 |
16138 | UKL/Kuingai/69 | Improvement of road from Kuingai to Tusom (SH:-Earth work, shingling and side drainage)- 10km | PWD | Ukhrul | 1 | Ongoing 45% | 01/03/2021 |
16139 | UKL/Kuingai/69 | Improvement of road from Kuingai to Tusom (SH:-Earth work, shingling and side drainage)- 10km | PWD | Ukhrul | 1 | Ongoing 45% | 01/03/2021 |
16140 | UKL/Kuingai/69 | Improvement of road from Kuingai to Tusom (SH:-Earth work, shingling and side drainage)- 10km | PWD | Ukhrul | 1 | Ongoing 45% | 01/03/2021 |