15061IED/Dolaithabi Internal Road/219M/o Dolaithabi Internal RoadPWDImphal-East1Completed06/10/2021
15062IED/Chingmeirong West/316M/o road Chingmeirong West 0.50 kmPWDImphal-East1stCompleted06/10/2021
15063IED/Road-Drain-Brindabon leirak/574M/o road and drain at Brindabon leirakPWDImphal-EastFinalcompleted06/10/2021
15064IED/Road Inside Mantrpiukhri CRPF/564M/o Internal road inside Mantripukhri CRPF CampPWDImphal-EastFinalCompleted06/10/2021
15065IWD/Maklang Maning-Sabal/226M/o road from Maklang maning to Sabal LeikaiPWDImphal-West1In progress06/10/2021
15066BPR/Impvt. of Ring Rd.../49.Impvt. of Ring Rd.Moirangkhunou Makha Leikai 1.20Kms.PWDBishnupurPhase IICompleted06/10/2021
15067BPR/Impvt. of Ring Rd.../49.Impvt. of Ring Rd.Moirangkhunou Makha Leikai 1.20Kms.PWDBishnupurPhase IICompleted06/10/2021
15068BPR/Impvt. of Rd.from Komjin.../48.Impvt. of Rd.from Komjin to Thanga Ckhinglak via. Thanga Tongbram.PWDBishnupurPhase IICompleted06/10/2021
15069IWD/RW-Kanglatombi Cremetorium/197Construction of retaining wall at Kanglatombi Crematorium road and restoration of damaged portion at Kanglatombi Crematorium roadPWDImphal-WestNACompleted06/10/2021
15070BPR/Impvt. of Rd.from Komjin.../48.Impvt. of Rd.from Komjin to Thanga Ckhinglak via. Thanga Tongbram.PWDBishnupurPhase IICompleted06/10/2021
15071IED/Officer Colony-Pureilomba/560Impvt. of road from Sanjenthong Officer Colony to Pureilomba KhongnangkhongPWDImphal-EastFinalCompleted06/10/2021
15072IWD/RCC Slab drain-BRTF/222Constn. of RCC slab drain cover at BRTF roadPWDImphal-WestNACompleted06/10/2021
15073EE/TPL/Wasaphai/5M/o road from Wasaphai to Lai-HaraochingPWDTengnoupalNaProgress06/10/2021
15074IED/Imp-Saikul- Diff SH/151M/o Imphal Saikul road (SH: Clearance of land slip, Kutcha drain, Hill cutting with Restoration of road pavement & protection work)PWDImphal-East1Completed06/10/2021
15075IED/Imp-Saikul- Diff SH/151M/o Imphal Saikul road (SH: Clearance of land slip, Kutcha drain, Hill cutting with Restoration of road pavement & protection work)PWDImphal-East1Completed06/10/2021
15076BRD/Khonghampat-RCCConstruction of bridge over Leimakhong river at Khonghampat KhunouPWDImphal-West899 percent06/10/2021
15077IED/Pukhao-Mapao kuki/153Impvt. of road from Pukhao to Mapao Kuki Village-3.00 kmPWDImphal-East1Completed06/10/2021
15078IED/culvert 3m-10.80 km/152Constn. of 3m span RCC culvert at 10.80 Km on Imphal saikul RoadPWDImphal-East1Completed06/10/2021
15079IED/Purana Rajbari-Muni/562Impvt. of approach road from Purana Rajbari-I to Mani Vision House i/c construction of pucca drainPWDImphal-EastFinalCompleted06/10/2021
15080IED/Chumbreithong-Khabam Phijam/188M/o road from Chumbreithong to Khabam Phijam LeirakPWDImphal-East2Completed06/10/2021