1321 | SE-I/DAR/24-25/IE.R1.846 Andro Parking | Strengthening and Widening of Wangkhei road at Andro Parking near Konung Mamang to Kongba Bridge | PWD | Imphal-East | ... | Completed | 13/02/2025 |
1322 | SE-I/DAR/24-25/IE.R1.846 Andro Parking | Strengthening and Widening of Wangkhei road at Andro Parking near Konung Mamang to Kongba Bridge | PWD | Imphal-East | ... | Completed | 13/02/2025 |
1323 | SE-I/DAR/24-25/IE.R1.846 Andro Parking | Strengthening and Widening of Wangkhei road at Andro Parking near Konung Mamang to Kongba Bridge | PWD | Imphal-East | --- | Completed | 13/02/2025 |
1324 | IED/Canchipur-Irilbung/234 | Impvt. of road from Canchipur MU gate (NH-39) to Irilbung via Jubraj Palli, Koirou, Bashikhong, Panthoibi Bazar and Konok Khongnangkhong (12.92 Km .. | PWD | Imphal-East | ---- | Completed | 13/02/2025 |
1325 | UKL/New heaven to Lamlang gate (old Ukl)A/118 | Impvt of road from New Heaven to Lamlang gate (old Ukhrul road) Ukhrul district Phase II 2 km | PWD | Ukhrul | Phase-II | 68% completed | 13/02/2025 |
1326 | UKL/New heaven to Lamlang gate (old Ukl)A/118 | Impvt of road from New Heaven to Lamlang gate (old Ukhrul road) Ukhrul district Phase II 2 km | PWD | Ukhrul | Phase-II | 68% completed | 13/02/2025 |
1327 | UKL/New heaven to Lamlang gate (old Ukl)A/118 | Impvt of road from New Heaven to Lamlang gate (old Ukhrul road) Ukhrul district Phase II 2 km | PWD | Ukhrul | Phase-II | 68% completed | 13/02/2025 |
1328 | UKL/New heaven to Lamlang gate (old Ukl)A/118 | Impvt of road from New Heaven to Lamlang gate (old Ukhrul road) Ukhrul district Phase II 2 km | PWD | Ukhrul | Phase-II | 68% completed | 13/02/2025 |
1329 | UKL/New heaven to Lamlang gate (old Ukl)A/118 | Impvt of road from New Heaven to Lamlang gate (old Ukhrul road) Ukhrul district Phase II 2 km | PWD | Ukhrul | Phase-II | 68% completed | 13/02/2025 |
1330 | IED/Kongba Kshetri Leikai-Khunou/332 | Impvt. of road from Kongba Kshetri Leikai to Khunou | PWD | Imphal-East | ---- | Completed | 13/02/2025 |
1331 | SE-I/DAR/20-21/CRIF/IE-R1.31 NH39 - Irilbung | Improvement of road from NH-39 to Irilbung via Kongba Irong | PWD | Imphal-East | --- | In progress 40 pc | 13/02/2025 |
1332 | UKL/Impvt of Raisheo Jn to Phalee Ukhrul /110 | Impvt of road from Raisheo Jn to Phalee village, Ukhrul district | PWD | Ukhrul | Phase-I | 68% completed | 13/02/2025 |
1333 | UKL/Impvt of Raisheo Jn to Phalee Ukhrul /110 | Impvt of road from Raisheo Jn to Phalee village, Ukhrul district | PWD | Ukhrul | Phase-I | 68% completed | 13/02/2025 |
1334 | UKL/Impvt of Raisheo Jn to Phalee Ukhrul /110 | Impvt of road from Raisheo Jn to Phalee village, Ukhrul district | PWD | Ukhrul | Phase-I | 68% completed | 13/02/2025 |
1335 | UKL/Impvt of Raisheo Jn to Phalee Ukhrul /110 | Impvt of road from Raisheo Jn to Phalee village, Ukhrul district | PWD | Ukhrul | Phase-I | 68% completed | 13/02/2025 |
1336 | SPT/Vaophea Junction to Kinafii colony/135 | Impvt of road from Vaophea Junction to Kinafii colony via Rodziikhao | PWD | Senapati | 1 | completed | 13/02/2025 |
1337 | SPT/Vaophea Junction to Kinafii colony/135 | Impvt of road from Vaophea Junction to Kinafii colony via Rodziikhao | PWD | Senapati | 1 | completed | 13/02/2025 |
1338 | SPT/Vaophea Junction to Kinafii colony/135 | Impvt of road from Vaophea Junction to Kinafii colony via Rodziikhao | PWD | Senapati | 1 | completed | 13/02/2025 |
1339 | SPT/Vaophea Junction to Kinafii colony/135 | Impvt of road from Vaophea Junction to Kinafii colony via Rodziikhao | PWD | Senapati | 1 | completed | 13/02/2025 |
1340 | SPT/Impvt of Napoukhovei to Fiimai gate/127 | Impvt of road from Napoukhovei to Fiimai gate | PWD | Senapati | 1 | completed | 13/02/2025 |