10641PAB/22-DI/SaitonHS/BishnupurStrengthening of Saiton High School under Samagra Shiksha for the year 2021-22, Bishnupur District.Education (S)BishnupurNillWork in progress20/10/2022
10642MSPCLC40Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Joujangtek, Noney District on turn key basisPOWER (MSPCL)Noney45%Under progress20/10/2022
10643WP/SainikgirlsHostel/IEConstruction of Girl's Hostel (Part - A) & (Part-B) at Sainik School, Imphal, ManipurEducation (S)Imphal-EastNilIn progress20/10/2022
10644WP/SainikgirlsHostel/IEConstruction of Girl's Hostel (Part - A) & (Part-B) at Sainik School, Imphal, ManipurEducation (S)Imphal-EastNilIn progress20/10/2022
10645WP/SainikgirlsHostel/IEConstruction of Girl's Hostel (Part - A) & (Part-B) at Sainik School, Imphal, ManipurEducation (S)Imphal-EastNilIn progress20/10/2022
10646WP/SainikgirlsHostel/IEConstruction of Girl's Hostel (Part - A) & (Part-B) at Sainik School, Imphal, ManipurEducation (S)Imphal-EastNilIn progress20/10/2022
10647SS/19-ChandrakhongPhanjangHS-TBLStrengthening and Residential Quarter under Samagra Shiksha, Manipur during 2019-20, Construction of 3 nos of Residential Quarter at Chandrakhong PhanEducation (S)ThoubalNilUnder Construction20/10/2022
10648SS/19-ChandrakhongPhanjangHS-TBLStrengthening and Residential Quarter under Samagra Shiksha, Manipur during 2019-20, Construction of 3 nos of Residential Quarter at Chandrakhong PhanEducation (S)ThoubalNilUnder Construction20/10/2022
10649SS/19-ChandrakhongPhanjangHS-TBLStrengthening and Residential Quarter under Samagra Shiksha, Manipur during 2019-20, Construction of 3 nos of Residential Quarter at Chandrakhong PhanEducation (S)ThoubalNilUnder Construction20/10/2022
10650SS/19-ChandrakhongPhanjangHS-TBLStrengthening and Residential Quarter under Samagra Shiksha, Manipur during 2019-20, Construction of 3 nos of Residential Quarter at Chandrakhong PhanEducation (S)ThoubalNilUnder Construction20/10/2022
10651MSPCLC46Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Liyaikhunou, Senapati DistrictPOWER (MSPCL)SenapatiNa30%20/10/2022
10652EE/SHD/BT Saikul-Makokching/40Being 1st install for Construction of road with black topping fro Saikul Bazar ( Police Station) to Makokching villagePWDKangpokpi2018-19100%20/10/2022
10653EE/SHD/BT Saikul-Makokching/40Being 1st install for Construction of road with black topping fro Saikul Bazar ( Police Station) to Makokching villagePWDKangpokpi2018-19100%20/10/2022
10654EE/SHD/1st.Install for Constn. Emou/41First install for- Constn. of road with black topping from Ekou to Ekou Mulam Nepali Basti.PWDKangpokpi2018-19100%20/10/2022
10655EE/SHD/1st.Install for Constn. Emou/41First install for- Constn. of road with black topping from Ekou to Ekou Mulam Nepali Basti.PWDKangpokpi2018-19100%20/10/2022
10656EE/SHD/1st.Install for Constn. Emou/41First install for- Constn. of road with black topping from Ekou to Ekou Mulam Nepali Basti.PWDKangpokpi2018-19100%20/10/2022
10657MSPCLB21Construction of 132 kV link transmission line for evacuation of power from 400/132 kV SS at Thoubal to 132 kV SS at Moreh on 132 kV line from KakchingPOWER (MSPCL)KakchingXYZ65%20/10/2022
10658MSPCLB21Construction of 132 kV link transmission line for evacuation of power from 400/132 kV SS at Thoubal to 132 kV SS at Moreh on 132 kV line from KakchingPOWER (MSPCL)KakchingXYZ65%20/10/2022
10659MSPCLC50Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Khongjaron, Tamenglong District on turn key baPOWER (MSPCL)TamenglongA4020/10/2022
10660MSPCLC49Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basisPOWER (MSPCL)JiribamA4020/10/2022