| 8521 | BD-I/PWD/RMD | Re-modelling of PWD (Block A, C, D & others office Buildings) at PWD Complex, Khoyathong | PWD | Imphal-West | Phase 3 | 100% Completed | 21/03/2023 |
| 8522 | BD-I/PWD/RMD | Re-modelling of PWD (Block A, C, D & others office Buildings) at PWD Complex, Khoyathong | PWD | Imphal-West | Phase 3 | 100% Completed | 21/03/2023 |
| 8523 | BD-I/PWD/RMD | Re-modelling of PWD (Block A, C, D & others office Buildings) at PWD Complex, Khoyathong | PWD | Imphal-West | Phase 3 | 100% Completed | 21/03/2023 |
| 8524 | BD-I/PWD/RMD | Re-modelling of PWD (Block A, C, D & others office Buildings) at PWD Complex, Khoyathong | PWD | Imphal-West | Phase 3 | 100% Completed | 21/03/2023 |
| 8525 | BD-I/PWD/RMD | Re-modelling of PWD (Block A, C, D & others office Buildings) at PWD Complex, Khoyathong | PWD | Imphal-West | Phase 3 | 100% Completed | 21/03/2023 |
| 8526 | BD-I/PWD/RMD | Re-modelling of PWD (Block A, C, D & others office Buildings) at PWD Complex, Khoyathong | PWD | Imphal-West | Phase 3 | 100% Completed | 21/03/2023 |
| 8527 | EE/Imp rd frm Mawai Jn to Tarong Nambashi/6 | Improvement of road from Mawai Jn.(BRTF) to Tarong- Nambashi (NH-102)road new Jn.in Kamjong District Part-1 | PWD | Kamjong | Phase I | In progress | 21/03/2023 |
| 8528 | UKL/Tashar Hatta/ 73 | Impvt. of road from Nungshang Kong to Tashar via Hatta | PWD | Ukhrul | 1 | completed | 21/03/2023 |
| 8529 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8530 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8531 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8532 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8533 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8534 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8535 | MSPDCL-STATEPLAN-101 | Supply of 35 no's of 250 KVA DTR, 30 no's of 100 KVA DTR, 20 no's of 63 KVA DTR & 15 no's of 25 KVA DTR as per IS:1180 (Part-I); 2014 | POWER (MSPDCL) | Imphal-West | NA | Work in Progress | 20/03/2023 |
| 8536 | Ukl/guest house/somdal/4059/2 | Constn. of Guest House at Somdal | PWD | Ukhrul | Phase 1 | Ongoing 35% | 20/03/2023 |
| 8537 | TML/New Takou Junction-Old Takou/48 | Impvt. of road New Takou Junction of Tamei Kuilong road to Old Takou - 10 Km | PWD | Tamenglong | I | On going | 20/03/2023 |
| 8538 | TML/New Takou Junction-Old Takou/48 | Impvt. of road New Takou Junction of Tamei Kuilong road to Old Takou - 10 Km | PWD | Tamenglong | I | On going | 20/03/2023 |
| 8539 | D3 Vokbual (L) P/S SS 2019-20 | Strengthening of School NR under Samagra Shiksha 2019-20 at Vokbual (L) P/S, Churachandpur District | Education (S) | Churachandpur | Nil | Inprogess | 20/03/2023 |
| 8540 | D3 Vokbual (L) P/S SS 2019-20 | Strengthening of School NR under Samagra Shiksha 2019-20 at Vokbual (L) P/S, Churachandpur District | Education (S) | Churachandpur | Nil | Inprogess | 20/03/2023 |