8281EE/TPL/Impvt. of rd in and around Tamil BastiImpvt. of road in and around Tamil Basti i/c Tamil Mandir road-1.3kmPWDTengnoupal1In Progress15/03/2023
8282EE/TPL/Impvt. of rd in and around Tamil BastiImpvt. of road in and around Tamil Basti i/c Tamil Mandir road-1.3kmPWDTengnoupal1In progress15/03/2023
8283SPT/Kayinu to Mao Ring road/62Improvement of Kayinu to Mao Ring road via ICCP - 4.50 kmPWDSenapatiPhase 1100 %15/03/2023
8284EE/TPL/Constn. of TD Block at Moreh/4Constn. of TD Block at Moreh.PWDTengnoupal1In progress15/03/2023
8285WRD-FCW-349Channelisation of Arong River at CharangpatWater Resources Department (WRD)ThoubalFinal phaseCompleted15/03/2023
8286KCG/Darpan/R&B/18-19/8Impvt. of road from Serou Lamkhai to serou Part - I.PWDKakching2nd& final100%15/03/2023
8287KCG/DARPAN/ROAD(P)/17Impvt.of road from Serou Lamkhai to Serou part I,II&III (15.00km)PWDKakching1100%15/03/2023
8288MSPCLC47Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Oinam, Senapati District on turn key basisPOWER (MSPCL)Senapatixxx50%15/03/2023
8289OR/NH-02/2022-23/Protection Work/450.196OR to NH-02 Churachandpur- Imphal Section, 2022-23, Construction of Protection Works at km 450.196PWDImphal-West1st and finalCompleted15/03/2023
8290OR/NH-02/2022-23/Protection Work/450.196OR to NH-02 Churachandpur- Imphal Section, 2022-23, Construction of Protection Works at km 450.196PWDImphal-West1st and finalCompleted15/03/2023
8291WRD-FCW-349Channelisation of Arong River at CharangpatWater Resources Department (WRD)ThoubalFinal phaseCompleted15/03/2023
8292WRD-FCW-349Channelisation of Arong River at CharangpatWater Resources Department (WRD)ThoubalFinal phaseCompleted15/03/2023
8293MSPCLC47Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Oinam, Senapati District on turn key basisPOWER (MSPCL)SenapatiX70%14/03/2023
8294MO/NH-202/Clearance/488M/O to NH-202, Imphal- Yaingangpokpi section, 2022-23 , Clearance of road side berm from km 468.00 to km 488.00PWDImphal-East1Completed14/03/2023
8295MO/NH-202/Clearance/488M/O to NH-202, Imphal- Yaingangpokpi section, 2022-23 , Clearance of road side berm from km 468.00 to km 488.00PWDImphal-East1Completed14/03/2023
8296SS/D-2-GelnalHrSec Lab- KPIStrengthening of Govt. Secondary & Higher Secondary School under Samagra Shiksha, Manipur 2021-22 at Gelnal Hr Sec School, Kangpokpi, Manipur.Education (S)KangpokpiNilUnder Construction14/03/2023
8297SS/D-2-GelnalHrSec Lab- KPIStrengthening of Govt. Secondary & Higher Secondary School under Samagra Shiksha, Manipur 2021-22 at Gelnal Hr Sec School, Kangpokpi, Manipur.Education (S)KangpokpiNilUnder Construction14/03/2023
8298M/O /NH-02/ Traffic IslandM/O to NH-02 Imphal-Yaingangpokpi section 2022-23, Construction of Traffic Island at Hodam leirak & Tiddim ground JunctionPWDImphal-West1Completed14/03/2023
8299SS/D-2-GelnalHrSec Lab- KPIStrengthening of Govt. Secondary & Higher Secondary School under Samagra Shiksha, Manipur 2021-22 at Gelnal Hr Sec School, Kangpokpi, Manipur.Education (S)KangpokpiNilUnder Construction14/03/2023
8300M/O /NH-02/ Traffic IslandM/O to NH-02 Imphal-Yaingangpokpi section 2022-23, Construction of Traffic Island at Hodam leirak & Tiddim ground JunctionPWDImphal-West1Completed14/03/2023