| 781 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | phase 1 | Completed | 24/03/2026 |
| 782 | RMSA/25-DI/Lamboikhongnangkhong100BoysHostel | Construction of 100 Bedded Hostel at Special Category Residential School Lamboikhongnangkhong, Imphal West | Education (S) | Imphal-West | nil | in progress | 24/03/2026 |
| 783 | RMSA/25-DI/Lamboikhongnangkhong100BoysHostel | Construction of 100 Bedded Hostel at Special Category Residential School Lamboikhongnangkhong, Imphal West | Education (S) | Imphal-West | nil | in progress | 24/03/2026 |
| 784 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | phase 1 | Completed | 24/03/2026 |
| 785 | RMSA/25-DI/Lamboikhongnangkhong100BoysHostel | Construction of 100 Bedded Hostel at Special Category Residential School Lamboikhongnangkhong, Imphal West | Education (S) | Imphal-West | nil | in progress | 24/03/2026 |
| 786 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | phase1 | Completed | 24/03/2026 |
| 787 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | phase 1 | Completed | 24/03/2026 |
| 788 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | Phase 1 | Ongoing | 24/03/2026 |
| 789 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | Phase 1 | Ongoing | 24/03/2026 |
| 790 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | phase 1 | completed | 24/03/2026 |
| 791 | MID-NABARD-XXVIII PW Sangaithel | Construction of Pick-up Weir across Heibirok stream at Sangaithel | Minor Irrigation Department | Imphal-West | phase1 | completed | 24/03/2026 |
| 792 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | phase 1 | material delivery | 24/03/2026 |
| 793 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | 2 phase | erection WIP | 24/03/2026 |
| 794 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | 2 phase | erection WIP | 24/03/2026 |
| 795 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | 2 phase | erection WIP | 24/03/2026 |
| 796 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | 2 phase | erection WIP | 24/03/2026 |
| 797 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | 2 phase | erection WIP | 24/03/2026 |
| 798 | MSPDCL-SASCI-114 | Supply & Laying of 11 KV XLPE AI Cable (3x300sq.mm.) for Underground Cabling (1.79x2 km-Double Run) | POWER (MSPDCL) | Imphal-West | 2 phase | erection WIP | 24/03/2026 |
| 799 | MSPCLC46 | Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Liyaikhunou, Senapati District | POWER (MSPCL) | Senapati | xx | 86.5% | 23/03/2026 |
| 800 | SS/23-D3/KakchingkhunouHS(Sc)/KAK | Construction of Upgraded High School to Higher Secondary School under Samagra Shiksha (Secondary) 2023-2024 at Kakching Khunou High School, Kakching, | Education (S) | Kakching | 2nd | work in progress | 23/03/2026 |