71981 | MID-IV-PMKSY-SPT-35-2020-21-Reiki Purul | Construction of P/W & I/C a/c Reiki river at Purul Akutpa Village | Minor Irrigation Department | Senapati | Pick up weir | Ongoing | |
71982 | MID-IV-PMKSY-SPT-35-2020-21-Reiki Purul | Construction of P/W & I/C a/c Reiki river at Purul Akutpa Village | Minor Irrigation Department | Senapati | Pick up weir | Ongoing | |
71983 | MSPDCL-CIVILWORK-066 | CONSTRUCTION OF DIVISIONAL OFFICE BUILDING AT PHERZAWL,MSPDCL | POWER (MSPDCL) | Pherzawl | Na | Na | |
71984 | MID-IV-PMKSY-SPT-35-2020-21-Reiki Purul | Construction of P/W & I/C a/c Reiki river at Purul Akutpa Village | Minor Irrigation Department | Senapati | Pick up weir | Ongoing | |
71985 | EDN(S)-MODHUMATI | Construction of Chowkidar Quarter at Modhumati Jr. High School, Bishnupur District (2011-12) | Education (S) | Bishnupur | Nil | Construction | |
71986 | MSPDCL-CIVILWORK-066 | CONSTRUCTION OF DIVISIONAL OFFICE BUILDING AT PHERZAWL,MSPDCL | POWER (MSPDCL) | Pherzawl | Na | Na | |
71987 | MID-IV-PMKSY-SPT-35-2020-21-Reiki Purul | Construction of P/W & I/C a/c Reiki river at Purul Akutpa Village | Minor Irrigation Department | Senapati | Pick up weir | Ongoing | |
71988 | MID-IV-PMKSY-SPT-35-2020-21-Reiki Purul | Construction of P/W & I/C a/c Reiki river at Purul Akutpa Village | Minor Irrigation Department | Senapati | Pick up weir | Ongoing | |
71989 | MSPDCL-CIVILWORK-066 | CONSTRUCTION OF DIVISIONAL OFFICE BUILDING AT PHERZAWL,MSPDCL | POWER (MSPDCL) | Pherzawl | Na | Na | |
71990 | IED/RW-RCC Culvert-Konok/610 | Construction of Retaining wall 100m and 2 nos. 1.5m span RCC culvert on western side of Konok Khongnangkhong | PWD | Imphal-East | 1 | Completed | |
71991 | IED/RW-RCC Culvert-Konok/610 | Construction of Retaining wall 100m and 2 nos. 1.5m span RCC culvert on western side of Konok Khongnangkhong | PWD | Imphal-East | 1 | Completed | |
71992 | UKL/Kuingai/69 | Improvement of road from Kuingai to Tusom (SH:-Earth work, shingling and side drainage)- 10km | PWD | Ukhrul | 1 | Ongoing 45% | |
71993 | MID-IV-PMKSY-KPI-14-2020-21-New salem | Construction of P/W & I/C Khaloubi stream at New Salem village | Minor Irrigation Department | Kangpokpi | 1 | Ongoing | |
71994 | MID-IV-PMKSY-KPI-14-2020-21-New salem | Construction of P/W & I/C Khaloubi stream at New Salem village | Minor Irrigation Department | Kangpokpi | 1 | Ongoing | |
71995 | Senapati CSC/Taklung | Construction of CSC under SBM at Taklung | PHED | Senapati | 1 | CSc | |
71996 | TEST-1 | TEST-1 | POWER (MSPDCL) | Imphal-West | NA | NA | |
71997 | TEST-1 | TEST-1 | POWER (MSPDCL) | Imphal-West | NA | NA | |
71998 | MID-IV-PMKSY-KPI-11-2020-21-Bliss lok | Construction of P/W & I/C at Bliss Lok at Moirangpan Village. | Minor Irrigation Department | Kangpokpi | 1 | Ongoing | |
71999 | TBL/Darpan/Plan/109 | Impvt.of Wangbal Awang Labuk road and Re-construction of 4m Span Slab Culvert over the Nongdambi River. | PWD | Thoubal | I | 60% | |
72000 | TBL/Darpan/Plan/109 | Impvt.of Wangbal Awang Labuk road and Re-construction of 4m Span Slab Culvert over the Nongdambi River. | PWD | Thoubal | I | 60% | |