70061 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | |
70062 | SS/19D-IBethaniPS | Strengthening of school-NR under Samagra Shiksha 2019-20 at Bethani Primary School, Noney | Education (S) | Noney | Nil | Completed | |
70063 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | |
70064 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | |
70065 | SS/19D-IBethaniPS | Strengthening of school-NR under Samagra Shiksha 2019-20 at Bethani Primary School, Noney | Education (S) | Noney | Nil | Completed | |
70066 | SS/19D-IBethaniPS | Strengthening of school-NR under Samagra Shiksha 2019-20 at Bethani Primary School, Noney | Education (S) | Noney | Nil | Completed | |
70067 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | |
70068 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70069 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70070 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | |
70071 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | |
70072 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70073 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70074 | 7/1/2020- PHE(10A)(Lubanglong - JJM) | Aug. of Water Supply scheme at Lubanglong | PHED | Noney | 1st phase | Ongoing | |
70075 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70076 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70077 | 7/1/2020- PHE(10A)(Lubanglong - JJM) | Aug. of Water Supply scheme at Lubanglong | PHED | Noney | 1st phase | Ongoing | |
70078 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70079 | UKL/Nungshong/65 | Impvt. of road (shingling & side drainage) from NH-150 Dungrei to Nungshong via Seipaikong 6th MR Bn. HQ & Tasar Oak farm (14 kms) | PWD | Ukhrul | 1 | Ongoing | |
70080 | TEST-1 | TEST-1 | POWER (MSPDCL) | Imphal-West | NA | NA | |