#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
6421SS/D-2-Langmeidong HSS- KKConstruction of 100 Bedded Hostel, Hostel (50 Bedded each for Boys & Girls) under Samagra Shiksha, Manipur during 2021-2022 for Langmeidong Hr. Sec. SEducation (S)KakchingnilUnder Construction18/07/2024
6422SDH/NH 2 to Phaohel via T. Lhanghoi/97Construction of road from NH-2 to Phaohel via T. LhanghoiPWDKangpokpi2023-2024100% completed18/07/2024
6423SDH/NH 2 to Phaohel via T. Lhanghoi/97Construction of road from NH-2 to Phaohel via T. LhanghoiPWDKangpokpi2023-2024100% completed18/07/2024
6424SDH/NH 2 to Phaohel via T. Lhanghoi/97Construction of road from NH-2 to Phaohel via T. LhanghoiPWDKangpokpi2023-2024100% completed18/07/2024
6425SDH/NH 2 to Phaohel via T. Lhanghoi/97Construction of road from NH-2 to Phaohel via T. LhanghoiPWDKangpokpi2023-2024100% completed18/07/2024
6426SDH/NH 2 to Phaohel via T. Lhanghoi/97Construction of road from NH-2 to Phaohel via T. LhanghoiPWDKangpokpi2023-2024100% completed18/07/2024
6427SDH/K Lhungwiram to K Ponlien via Tangnom/95Construction of road from K. Lhungwira t K. Ponlien via Tangnom (Haraothel), Karoram Vaiphei and IrengPWDKangpokpi2023-2024100% completed18/07/2024
6428SDH/K Lhungwiram to K Ponlien via Tangnom/95Construction of road from K. Lhungwira t K. Ponlien via Tangnom (Haraothel), Karoram Vaiphei and IrengPWDKangpokpi2023-2024100% completed18/07/2024
6429SDH/K Lhungwiram to K Ponlien via Tangnom/95Construction of road from K. Lhungwira t K. Ponlien via Tangnom (Haraothel), Karoram Vaiphei and IrengPWDKangpokpi2023-2024100% completed18/07/2024
6430SEIV/Impvt of Vaki to Phuba-4km/74Impvt of road from Vaki to Phuba-4kmPWDSenapati1completed17/07/2024
6431SEIV/Impvt of Vaki to Phuba-4km/74Impvt of road from Vaki to Phuba-4kmPWDSenapati1completed17/07/2024
6432SEIV/Impvt from Vaki to Phuba 4km/75Impvt of road from Vaki to Phuba - 4kmPWDSenapati1completed17/07/2024
6433UKL/Kachai PMGSY road to kachaithikhor/60Improvement of road from Kachai PMGSY road to KachaithikhorPWDUkhrul190% 17/07/2024
6434UKL/Kachai PMGSY road to kachaithikhor/60Improvement of road from Kachai PMGSY road to KachaithikhorPWDUkhrul190% 17/07/2024
6435UKL/Kachai PMGSY road to kachaithikhor/60Improvement of road from Kachai PMGSY road to KachaithikhorPWDUkhrul190% 17/07/2024
6436UKL/Kachai PMGSY road to kachaithikhor/60Improvement of road from Kachai PMGSY road to KachaithikhorPWDUkhrul190% 17/07/2024
6437UKL/Kachai PMGSY road to kachaithikhor/60Improvement of road from Kachai PMGSY road to KachaithikhorPWDUkhrul190% 17/07/2024
6438UKL/Kachai PMGSY road to kachaithikhor/60Improvement of road from Kachai PMGSY road to KachaithikhorPWDUkhrul190% 17/07/2024
6439UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul2completed17/07/2024
6440UKL/SE-IV/Maichon JN to Iril bridge/38 Impvt. of road from Maichon Jn to Iril Bailey bridgePWDUkhrul1completed 17/07/2024