| 5141 | SS/D-2-Langmeidong HSS- KK | Construction of 100 Bedded Hostel, Hostel (50 Bedded each for Boys & Girls) under Samagra Shiksha, Manipur during 2021-2022 for Langmeidong Hr. Sec. S | Education (S) | Kakching | nil | Under Construction | 18/07/2024 | 
| 5142 | SDH/NH 2 to Phaohel via T. Lhanghoi/97 | Construction of road from NH-2 to Phaohel via T. Lhanghoi | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5143 | SDH/NH 2 to Phaohel via T. Lhanghoi/97 | Construction of road from NH-2 to Phaohel via T. Lhanghoi | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5144 | SDH/NH 2 to Phaohel via T. Lhanghoi/97 | Construction of road from NH-2 to Phaohel via T. Lhanghoi | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5145 | SDH/NH 2 to Phaohel via T. Lhanghoi/97 | Construction of road from NH-2 to Phaohel via T. Lhanghoi | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5146 | SDH/NH 2 to Phaohel via T. Lhanghoi/97 | Construction of road from NH-2 to Phaohel via T. Lhanghoi | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5147 | SDH/K Lhungwiram to K Ponlien via Tangnom/95 | Construction of road from K. Lhungwira t K. Ponlien via Tangnom (Haraothel), Karoram Vaiphei and Ireng | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5148 | SDH/K Lhungwiram to K Ponlien via Tangnom/95 | Construction of road from K. Lhungwira t K. Ponlien via Tangnom (Haraothel), Karoram Vaiphei and Ireng | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5149 | SDH/K Lhungwiram to K Ponlien via Tangnom/95 | Construction of road from K. Lhungwira t K. Ponlien via Tangnom (Haraothel), Karoram Vaiphei and Ireng | PWD | Kangpokpi | 2023-2024 | 100% completed | 18/07/2024 | 
| 5150 | SDH/Const. of road Bethel to Haraothel/93 | Construction of road from Bethel to Haraothel | PWD | Kangpokpi | 2023-2024 | 75% | 18/07/2024 | 
| 5151 | SDH/Const. of road Bethel to Haraothel/93 | Construction of road from Bethel to Haraothel | PWD | Kangpokpi | 2023-2024 | 75% | 18/07/2024 | 
| 5152 | SEIV/Impvt of Vaki to Phuba-4km/74 | Impvt of road from Vaki to Phuba-4km | PWD | Senapati | 1 | completed | 17/07/2024 | 
| 5153 | SEIV/Impvt of Vaki to Phuba-4km/74 | Impvt of road from Vaki to Phuba-4km | PWD | Senapati | 1 | completed | 17/07/2024 | 
| 5154 | SEIV/Impvt from Vaki to Phuba 4km/75 | Impvt of road from Vaki to Phuba - 4km | PWD | Senapati | 1 | completed | 17/07/2024 | 
| 5155 | UKL/Kachai PMGSY road to kachaithikhor/60 | Improvement of road from Kachai PMGSY road to Kachaithikhor | PWD | Ukhrul | 1 | 90%  | 17/07/2024 | 
| 5156 | UKL/Kachai PMGSY road to kachaithikhor/60 | Improvement of road from Kachai PMGSY road to Kachaithikhor | PWD | Ukhrul | 1 | 90%  | 17/07/2024 | 
| 5157 | UKL/Kachai PMGSY road to kachaithikhor/60 | Improvement of road from Kachai PMGSY road to Kachaithikhor | PWD | Ukhrul | 1 | 90%  | 17/07/2024 | 
| 5158 | UKL/Kachai PMGSY road to kachaithikhor/60 | Improvement of road from Kachai PMGSY road to Kachaithikhor | PWD | Ukhrul | 1 | 90%  | 17/07/2024 | 
| 5159 | UKL/Kachai PMGSY road to kachaithikhor/60 | Improvement of road from Kachai PMGSY road to Kachaithikhor | PWD | Ukhrul | 1 | 90%  | 17/07/2024 | 
| 5160 | UKL/Kachai PMGSY road to kachaithikhor/60 | Improvement of road from Kachai PMGSY road to Kachaithikhor | PWD | Ukhrul | 1 | 90%  | 17/07/2024 |