| 4821 | UKL/Repairing South Block DC MiniSec/155 | Renovation/Repairing of South block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | completed | 05/02/2025 |
| 4822 | UKL/Repairing South Block DC MiniSec/155 | Renovation/Repairing of South block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | completed | 05/02/2025 |
| 4823 | UKL/Repairing North Block DC MiniSec/153 | Renovation/Repairing of north block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | 49% progress | 05/02/2025 |
| 4824 | UKL/Repairing North Block DC MiniSec/153 | Renovation/Repairing of north block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | 49% progress | 05/02/2025 |
| 4825 | UKL/Repairing North Block DC MiniSec/153 | Renovation/Repairing of north block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | phase 1 | 49% | 05/02/2025 |
| 4826 | UKL/Repairing West Block DC block MiniSec/153 | Renovation/Repairing of west block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | 53% progress | 05/02/2025 |
| 4827 | UKL/Repairing West Block DC block MiniSec/153 | Renovation/Repairing of west block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | 53% progress | 05/02/2025 |
| 4828 | UKL/Repairing West Block DC block MiniSec/153 | Renovation/Repairing of west block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | Phase 1 | 53% | 05/02/2025 |
| 4829 | SEIV/impvt from NH-202 to 132kv Substatn/64 | Impvt of road from NH-202 to 132 KV Substation, MSPDCL, Ukhrul Subhead widening and road pavement | PWD | Ukhrul | 2023-2024 | 50% progress | 05/02/2025 |
| 4830 | SEIV/impvt from NH-202 to 132kv Substatn/64 | Impvt of road from NH-202 to 132 KV Substation, MSPDCL, Ukhrul Subhead widening and road pavement | PWD | Ukhrul | 2023-2024 | 50% progress | 05/02/2025 |
| 4831 | SEIV/impvt from NH-202 to 132kv Substatn/64 | Impvt of road from NH-202 to 132 KV Substation, MSPDCL, Ukhrul Subhead widening and road pavement | PWD | Ukhrul | 2023-2024 | 50% progress | 05/02/2025 |
| 4832 | SEIV/impvt from NH-202 to 132kv Substatn/63 | Impvt of road from NH-202 to 132 KV Substation, MSPDCL, Ukhrul Subhead Construction of pipe culverts & retaining wall | PWD | Ukhrul | 2023-2024 | 70% progress | 05/02/2025 |
| 4833 | SEIV/impvt from NH-202 to 132kv Substatn/63 | Impvt of road from NH-202 to 132 KV Substation, MSPDCL, Ukhrul Subhead Construction of pipe culverts & retaining wall | PWD | Ukhrul | 2023-2024 | 70% progress | 05/02/2025 |
| 4834 | SEIV/impvt from NH-202 to 132kv Substatn/63 | Impvt of road from NH-202 to 132 KV Substation, MSPDCL, Ukhrul Subhead Construction of pipe culverts & retaining wall | PWD | Ukhrul | 2023-2024 | 70% progress | 05/02/2025 |
| 4835 | BD-II/AE-III/Qtr.No.15 Ex-CM | Renovation of Qtr.No.15 at Babupara.(Ex-CM) | PWD | Imphal-West | I | 100 | 05/02/2025 |
| 4836 | BD-II/AE-III/Qtr.No.15 Ex-CM | Renovation of Qtr.No.15 at Babupara.(Ex-CM) | PWD | Imphal-West | I | 100 | 05/02/2025 |
| 4837 | D-IV/Y.K/CFM | Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Y. K. College,Thoubal, Manipur. | Education (S) | Thoubal | 2nd | The work has been complete upto roof beam | 05/02/2025 |
| 4838 | BD-II/AE-III/Qtr.No.15 Ex-CM | Renovation of Qtr.No.15 at Babupara.(Ex-CM) | PWD | Imphal-West | I | 100 | 05/02/2025 |
| 4839 | BD-II/AE-III/Qtr.No.15 Ex-CM | Renovation of Qtr.No.15 at Babupara.(Ex-CM) | PWD | Imphal-West | I | 100 | 05/02/2025 |
| 4840 | UKL/Repairing East Block DC block MiniSec/154 | Renovation/Repairing of East block (DC Block) of Mini Secretariat, Ukhrul | PWD | Ukhrul | 2023-2024 | completed | 05/02/2025 |