4281 | IED/Approach road-Shishu Nistha Niketan/896 | Constn. of approach road from Tinsid road leading to Shishu Nistha Niketan, Chinghei Ching, Imphal East. | PWD | Imphal-East | --- | Completed | 17/07/2024 |
4282 | IED/ Kongba Maril Khabeisoi(western)/901 | Impvt. of Kongba Maril Khabeisoi road (Western side of Kongba river | PWD | Imphal-East | -- | Completed | 17/07/2024 |
4283 | IED/Bamon_Tharoijam via Paonam leirak/895 | Impvt. of Bamon leirak, Tharoijam leirak via Paonam leirak | PWD | Imphal-East | -- | completed | 17/07/2024 |
4284 | IED/Return Wall-Top Khongnangkhong Bridge/862 | Contn. of Return Wall at Top Khongnangkhong Bridge, Kshetrigao A/C, Imphal east | PWD | Imphal-East | -- | Completed | 17/07/2024 |
4285 | IED/Porompat road No. II/902 | Impvt. of Porompat road No. II | PWD | Imphal-East | -- | Completed | 16/07/2024 |
4286 | IED/Standard College Road/882 | Improvement of Standard College Road. | PWD | Imphal-East | -- | Completed | 16/07/2024 |
4287 | IED/Kongpal Iranpham-Thambalkhong/891 | Improvement of Road from Kongpal Iranpham Thong to Thambalkhong eastern side Kongba Bazar | PWD | Imphal-East | -- | Completed | 16/07/2024 |
4288 | UKL/SE-IV/Luimeirui to Khayang rover tuso/39 | Impvt. of road from Luimeirui to Khayang Rover PMGSY road North Tusom | PWD | Ukhrul | Phase 2 | 80% | 16/07/2024 |
4289 | UKL/SE-IV/Luimeirui to Khayang rover tuso/39 | Impvt. of road from Luimeirui to Khayang Rover PMGSY road North Tusom | PWD | Ukhrul | Phase 2 | 80% | 16/07/2024 |
4290 | UKL/SE-IV/Luimeirui to Khayang rover tuso/39 | Impvt. of road from Luimeirui to Khayang Rover PMGSY road North Tusom | PWD | Ukhrul | Phase 2 | 80% | 16/07/2024 |
4291 | UKL/Tolloi NH 102A junction to Phungcham/61 | Construction of road from Tolloi NH 102A Junction to Phungcham | PWD | Ukhrul | Phase 2 | 80% | 16/07/2024 |
4292 | UKL/Tolloi NH 102A junction to Phungcham/61 | Construction of road from Tolloi NH 102A Junction to Phungcham | PWD | Ukhrul | Phase 2 | 80% | 16/07/2024 |
4293 | UKL/Tolloi NH 102A junction to Phungcham/61 | Construction of road from Tolloi NH 102A Junction to Phungcham | PWD | Ukhrul | Phase 2 | 80% | 16/07/2024 |
4294 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |
4295 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |
4296 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |
4297 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |
4298 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |
4299 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |
4300 | UKL/SE-IV/Intervillage Circular road Tusom/9 | Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian Village | PWD | Ukhrul | Phase 1 | 60% | 16/07/2024 |