Project Updates
Showing 42,501-42,520 of 88,456 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
42501MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42502MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42503MSPCLC53Installation of 2x2.5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Nampisha, Kamjong District on turn key basisPOWER (MSPCL)Kamjong160%
42504BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompletedcompleted
42505BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42506BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42507BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42508BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42509WRD-WB-06Rejuvenation of Lamphelpat Waterbody(SH - Construction of bridge for motors, pedestrians etc. at Lamphelpat, Imphal West, Manipur)Water Resources Department (WRD)Imphal-WestPile Reinforcement Ongoing
42510WRD-WB-06Rejuvenation of Lamphelpat Waterbody(SH - Construction of bridge for motors, pedestrians etc. at Lamphelpat, Imphal West, Manipur)Water Resources Department (WRD)Imphal-WestFoundation workongoing
42511BRD/Bridge-Sun Light Club/24Constn. of RCC Bridge Kongba River at Sun Light Club MapaPWDImphal-Eastfinalcompleted
42512SE-I/IE/DRP/2023-24/R1/17-1-RIDF SawombungImprovement of road from Sawombung to Sagolmang Bazar via KeibiPWDImphal-Eastmid phaseongoing work
42513SE-I/IE/DRP/2023-24/R1/17-1-RIDF SawombungImprovement of road from Sawombung to Sagolmang Bazar via KeibiPWDImphal-Eastmid phaseongoing work
42514SE-I/DRP/2023-24/Rc-78 -Lei Ingkhol 1m SCConstruction of drain at Chingmeirong Lei Ingkhol including 1 m span RCC slab culvertPWDImphal-EastNA100%
42515SE-I/DRP/2023-24/R1-69 -drain at AT LineImprovement of road and drain at AT LinePWDImphal-EastNA100%
42516IED/Iranpham-Ukhrul(eastern side-Kongba)/898Impvt. of road connecting Iranpham to Ukhrul road (eastern side of Kongba river)PWDImphal-East3rdcomoleted
42517IED/NE School-Tinsid_Lai Puri/887Improvement of North Eastern School connecting Tinsid road & Lai Puri PurabaPWDImphal-East3rdWBM
42518IED/Approach road-Shishu Nistha Niketan/896Constn. of approach road from Tinsid road leading to Shishu Nistha Niketan, Chinghei Ching, Imphal East.PWDImphal-East2ndongoing
42519WSM-II-CHINGKHEICHINGConstruction of Water Treatment Plant at Chingkheiching (45.00 MLD Capacity) for Imphal CityPHEDImphal-Eastslope protection workwork in progress
42520WSM-II-CHINGKHEICHINGConstruction of Water Treatment Plant at Chingkheiching (45.00 MLD Capacity) for Imphal CityPHEDImphal-Eastslope protection workwork in progress