39861CCP/impvt of Lower Kom Keirap Road/142Improvement of Lower Kom Keirap Road 1.5 KmPWDChurachandpurphase 172% progress
39862CCP/impvt of Lower Kom Keirap Road/142Improvement of Lower Kom Keirap Road 1.5 KmPWDChurachandpurphase 1 72% progress
39863CCP/impvt of Lower Kom Keirap Road/142Improvement of Lower Kom Keirap Road 1.5 KmPWDChurachandpurphase 172% progress
39864CCP/ Lower Keirap to PHSC Upper Kom Rwal /141Construction of road from Lower Keirap to PHSC at Upper Kom Keirap with retaining wall of 30 meters 1 kmPWDChurachandpurPhase 161% progress
39865CCP/ Lower Keirap to PHSC Upper Kom Rwal /141Construction of road from Lower Keirap to PHSC at Upper Kom Keirap with retaining wall of 30 meters 1 kmPWDChurachandpurPhase 161% progress
39866CCP/ Lower Keirap to PHSC Upper Kom Rwal /141Construction of road from Lower Keirap to PHSC at Upper Kom Keirap with retaining wall of 30 meters 1 kmPWDChurachandpurPhase 161% progress
39867CCP/constn of drain at Upper Kom Keirap/140Construction of drain at Upper Kom Keirap 2 KmPWDChurachandpurphase 162%
39868CCP/constn of drain at Upper Kom Keirap/140Construction of drain at Upper Kom Keirap 2 KmPWDChurachandpurPhase 162%
39869CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162%
39870CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162%
39871CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162% progress
39872CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162%
39873SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 162% completed
39874SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 162% completed
39875SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 1Ongoing (62%)
39876SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 162% completed
39877SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 162% completed
39878SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 162% completed
39879CDL/renovation of minisectariat chandel/58Renovation of Mini Secretariat, ChandelPWDChandelProfile RoofingCompleted
39880EE/Upgrdtn of rd in and around Thanga Part-IIUpgradation of roads in and around Thanga Part-II 10.00 kmPWDBishnupurphase Iin progress