Project Updates
Showing 30,861-30,880 of 32,363 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
30861UKL/Impvt of internal road Shimtang Ukhru/105Impvt of Internal road Shimtang Ukhrul (2 km)PWDUkhrulPhase-I85%
30862EE/BPR/Impvt Kumbi Saiton roadImprovement of Kumbi Saiton RoadPWDBishnupur1work is in progress97pc
30863UKL/SE-IV/Intervillage Circular road Tusom/9Impvt. of Intervillage Circular road at a) New Tusom and b) Tusom Christian VillagePWDUkhrulPhase 1completed
30864UKL/DAR/2023-24/3/Mathuk bridge to Lamlang Improvement of road from Mathuk bridge to Lamlang gate, Ukhrul district SH Construction of 2 RCC Slab culvertsPWDUkhrulPhase-I97%
30865UKL/DAR/2023-24/3/Mathuk bridge to Lamlang Improvement of road from Mathuk bridge to Lamlang gate, Ukhrul district SH Construction of 2 RCC Slab culvertsPWDUkhrulPhase-I97%
30866UKL/Somdal chapel crossing to RV Themthin/120Somdal Chapel crossing to RV TGhemthing are measuring about 1.2km for WBM and BlacktoppingPWDUkhrulPhase--I61.1%
30867EE/TBL/Darpan/CRIF(P)/128Improvement of Thoubal M.I road(SH-5.30km to 15.50km)PWDThoubal290%
30868CCP/impvt of Lower Kom Keirap Road/142Improvement of Lower Kom Keirap Road 1.5 KmPWDChurachandpurphase 172% progress
30869CCP/impvt of Lower Kom Keirap Road/142Improvement of Lower Kom Keirap Road 1.5 KmPWDChurachandpurphase 1 72% progress
30870CCP/impvt of Lower Kom Keirap Road/142Improvement of Lower Kom Keirap Road 1.5 KmPWDChurachandpurphase 172% progress
30871CCP/ Lower Keirap to PHSC Upper Kom Rwal /141Construction of road from Lower Keirap to PHSC at Upper Kom Keirap with retaining wall of 30 meters 1 kmPWDChurachandpurPhase 161% progress
30872CCP/ Lower Keirap to PHSC Upper Kom Rwal /141Construction of road from Lower Keirap to PHSC at Upper Kom Keirap with retaining wall of 30 meters 1 kmPWDChurachandpurPhase 161% progress
30873CCP/ Lower Keirap to PHSC Upper Kom Rwal /141Construction of road from Lower Keirap to PHSC at Upper Kom Keirap with retaining wall of 30 meters 1 kmPWDChurachandpurPhase 161% progress
30874CCP/constn of drain at Upper Kom Keirap/140Construction of drain at Upper Kom Keirap 2 KmPWDChurachandpurphase 162%
30875CCP/constn of drain at Upper Kom Keirap/140Construction of drain at Upper Kom Keirap 2 KmPWDChurachandpurPhase 162%
30876CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162%
30877CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162%
30878CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162% progress
30879CCP/Chingei Pangyang to NH-150 via Haotak/139Impvt. of Chingei Pangyang to NH-150 via Haotak 3.7 kmPWDChurachandpurphase 162%
30880SPT/Khousabung to NH-150 via Ngangkhalawa/138Impvt. of Khousabung to NH-150 via Ngangkhalawai Amukhul and S. Phainom-3.6 kmPWDChurachandpurphase 162% completed