| 28161 | IED/RCC culvert-Keishamthong/109 | Constn. of 2.00 m span RCC slab culvert at Keishamthong road. | PWD | Imphal-East | NA | In progress | 17/03/2018 |
| 28162 | IWD/NH-150-37-Heigrujam/50 | Impvt. of work programme NH(150-37) to Heigrujam via Kangmong Langoijam | PWD | Imphal-West | 2nd phase | Completed | 17/03/2018 |
| 28163 | IWD/NH-150-37-Heigrujam/50 | Impvt. of work programme NH(150-37) to Heigrujam via Kangmong Langoijam | PWD | Imphal-West | 2nd phase | Completed | 17/03/2018 |
| 28164 | IWD/NH-37-Konthoujam Lairembi/51 | Impvt. of NH-37 to Konthoujam Lairembi via Konthoujam Makha Leikai | PWD | Imphal-West | 2nd phase | Completed | 17/03/2018 |
| 28165 | IWD/NH-37-Konthoujam Lairembi/51 | Impvt. of NH-37 to Konthoujam Lairembi via Konthoujam Makha Leikai | PWD | Imphal-West | 2nd phase | Completed | 17/03/2018 |
| 28166 | IED/Minuthong-Lamlong Bridge/118 | Maint. of road from Minuthong to Lamlong Bridge via Khuman Lampak | PWD | Imphal-East | NA | In progress | 17/03/2018 |
| 28167 | IED/Minuthong-Lamlong Bridge/118 | Maint. of road from Minuthong to Lamlong Bridge via Khuman Lampak | PWD | Imphal-East | NA | In progress | 17/03/2018 |
| 28168 | IED/Minuthong-Lamlong Bridge/118 | Maint. of road from Minuthong to Lamlong Bridge via Khuman Lampak | PWD | Imphal-East | NA | In progress | 17/03/2018 |
| 28169 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
| 28170 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
| 28171 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
| 28172 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
| 28173 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
| 28174 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
| 28175 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
| 28176 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 28177 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 28178 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 28179 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
| 28180 | IWD/Haorang Keirel-Khoriphaba/30 | Impvt. of Haorang Keirel to Khoriphaba. | PWD | Imphal-West | 1 | In progress | 15/03/2018 |