25261 | IWD/NH-37-Konthoujam Lairembi/51 | Impvt. of NH-37 to Konthoujam Lairembi via Konthoujam Makha Leikai | PWD | Imphal-West | 2nd phase | Completed | 17/03/2018 |
25262 | IED/Minuthong-Lamlong Bridge/118 | Maint. of road from Minuthong to Lamlong Bridge via Khuman Lampak | PWD | Imphal-East | NA | In progress | 17/03/2018 |
25263 | IED/Minuthong-Lamlong Bridge/118 | Maint. of road from Minuthong to Lamlong Bridge via Khuman Lampak | PWD | Imphal-East | NA | In progress | 17/03/2018 |
25264 | IED/Minuthong-Lamlong Bridge/118 | Maint. of road from Minuthong to Lamlong Bridge via Khuman Lampak | PWD | Imphal-East | NA | In progress | 17/03/2018 |
25265 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25266 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25267 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25268 | IWD/Thangmeiband AC/41 | Impvt. of road in and around Thangmeiband A/C | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25269 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
25270 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
25271 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | X | 100 | 15/03/2018 |
25272 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
25273 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
25274 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
25275 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | X | 100 percent completed | 15/03/2018 |
25276 | IWD/Haorang Keirel-Khoriphaba/30 | Impvt. of Haorang Keirel to Khoriphaba. | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25277 | IWD/Lamsang-Sekami/42 | Impvt. of Lamsang Sekmai Road (Left out portion - 1.30 Km) | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25278 | IWD/Lamsang-Sekami/42 | Impvt. of Lamsang Sekmai Road (Left out portion - 1.30 Km) | PWD | Imphal-West | 1 | In progress | 15/03/2018 |
25279 | Imphal Sewrage Project, Phase-I | Imphal Sewerage Project phase-I for Imphal Town with French Assistance | PHED | Imphal-West | Phase i | Ongoing | 15/03/2018 |
25280 | Imphal Sewrage Project, Phase-I | Imphal Sewerage Project phase-I for Imphal Town with French Assistance | PHED | Imphal-West | Phase i | Ongoing | 15/03/2018 |