#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
22861UKL/Kuilungtang/39Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km.PWDUkhrulPhase -lConstruction in Progress07/01/2019
22862UKL/Kuilungtang/39Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km.PWDUkhrulPhase -lConstruction in Progress07/01/2019
22863UKL/Kuilungtang/39Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km.PWDUkhrulPhase -lConstruction07/01/2019
22864UKL/Kuilungtang/39Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km.PWDUkhrulPhase -lConstruction in Progress (Lower Road)07/01/2019
22865UKL/Kuilungtang/39Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km.PWDUkhrulPhase -lConstruction in Progress07/01/2019
22866UKL/Kuilungtang/39Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km.PWDUkhrulPhase -lConstruction07/01/2019
22867MQCD/Darpan/Luwangsangbam/PM/2018-19/35Preparation of Infrastructures in connection with the Inauguration & laying of Foundation Stones by the P.M of India at Luwangpokpa Cricket Stadium.PWDImphal-East1Completed03/01/2019
22868MQCD/Darpan/Luwangsangbam/PM/2018-19/35Preparation of Infrastructures in connection with the Inauguration & laying of Foundation Stones by the P.M of India at Luwangpokpa Cricket Stadium.PWDImphal-East1Completed03/01/2019
22869MQCD/Darpan/Luwangsangbam/PM/2018-19/35Preparation of Infrastructures in connection with the Inauguration & laying of Foundation Stones by the P.M of India at Luwangpokpa Cricket Stadium.PWDImphal-East1Completed03/01/2019
22870TBL/Darpan/Plan/53Impt of Yairipok Bazar to Shikhong road-7.50km(SH:-Strengthening of road from 4.00km to 6.00km)PWDThoubalPhase 145%03/01/2019
22871TBL/Darpan/Plan/53Impt of Yairipok Bazar to Shikhong road-7.50km(SH:-Strengthening of road from 4.00km to 6.00km)PWDThoubalPhase 145%03/01/2019
22872RMSA/17-KhoiripokUPS-UKLUpgradation of Jr. High School to High School under RMSA of Khoiripok Upper Primary School, UkhrulEducation (S)UkhrulNillIn progess31/12/2018
22873project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurFinal phase.Complete.29/12/2018
22874project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurFinal phase.Complete.29/12/2018
22875project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurCompleteFinal29/12/2018
22876project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurCompleteFinal29/12/2018
22877project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurCompleteFinal29/12/2018
22878project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurCompleteFinal29/12/2018
22879project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurCompleteFinal29/12/2018
22880project-06-ccpur cercuitConstruction of Circuit House Churachandpur, Churachandpur townPlanning DepartmentChurachandpurFinal phase.Complete.29/12/2018