| 41 | EE/BPR/Recontn damaged Northern side compound | Recontn of damaged Northern side Compound wall of PWD , Moirang Sub-Division i/c land development | PWD | Bishnupur | 1 | Work is in progress65pc | 18/10/2024 |
| 42 | EE/BPR/Major Renovatn AE(PWD) office Staff | Major Renovation of AE(PWD)office & Staff Quarter at Moirang | PWD | Bishnupur | 1 | Work is in progress60pc | 18/10/2024 |
| 43 | EE/BPR/Impvt Kha Thinungei IVR via VDFpost | Improvement of Kha Thinungei IVR via VDFpost-2.10km | PWD | Bishnupur | 2 | work is in progress | 18/10/2024 |
| 44 | EE/BPR/Renovation SDC Office IEI | Renovation of SDC Office with IEI, Moirang | PWD | Bishnupur | 1 | Work is in progress | 01/07/2024 |
| 45 | EE/BPR/Major Renovatn AE(PWD) office Staff | Major Renovation of AE(PWD)office & Staff Quarter at Moirang | PWD | Bishnupur | 2 | work is in progress | 29/10/2024 |
| 46 | EE/BPR/Impvt Moirangkhunou Mamang Sabal | Improvement of Moirangkhunou Mamang Sabal ring road-1.5km | PWD | Bishnupur | 2 | work is in progress | 18/10/2024 |
| 47 | EE/BPR/Impvt. of road from Pengba Farm to Gel | Impvt. of road from Pengba Farm to Gelbung | PWD | Bishnupur | 2 | work is in progress | 26/09/2024 |
| 48 | EE/BPR/Impvt rd Kumbi Sagolpat to Saiton | Improvement of road from Kumbi Sagolpat to Saiton awang leikai with 1m span culverts.(2nos) | PWD | Bishnupur | 2 | work is in progress | |
| 49 | EE/BPR/Impt. of Ithai Khunou Govt. high schoo | Impvt. of Ithai Khunou Govt. High school to Athokpam Mapa | PWD | Bishnupur | 2 | work is in progress | 26/09/2024 |
| 50 | EE/BPR/Impvt rd Wathalambi Lamlong | Improvement of road from Wathalambi Lamlong to Anandpur IVR-2.5km | PWD | Bishnupur | 2 | work is in progress | |
| 51 | SPT/Road/MaramDonBoscoCollege/26 | Impvt. of approach road of Maram Donbosco college | PWD | Senapati | Phase 1 | Work in progress: Drain to be done | 05/03/2019 |
| 52 | EE/JBM/Impvt rd Uchathol Khasi to Jaral Pokpi | Impvt. of road from Uchathol Khasi to Jaral pokpi Mushlim via Police training centre | PWD | Jiribam | phase I | Work in progress82.10pc | 17/03/2025 |
| 53 | 100DAYS/NH-02&NH-137A/2022-23 | Beautification of roads of National Highways along Greater Imphal Area by providing bituminous layer on unpaved portion. | PWD | Imphal-West | 100 days programme | Work in progress, 100 days progress | 17/01/2023 |
| 54 | 100DAYS/NH-02&NH-137A/2022-23 | Beautification of roads of National Highways along Greater Imphal Area by providing bituminous layer on unpaved portion. | PWD | Imphal-West | 100 days programme | Work in progress, 100 days progress | 17/01/2023 |
| 55 | 100DAYS/NH-02&NH-137A/2022-23 | Beautification of roads of National Highways along Greater Imphal Area by providing bituminous layer on unpaved portion. | PWD | Imphal-West | 100 days programme | Work in progress, 100 days progress | 17/01/2023 |
| 56 | 100DAYS/NH-02&NH-137A/2022-23 | Beautification of roads of National Highways along Greater Imphal Area by providing bituminous layer on unpaved portion. | PWD | Imphal-West | 100 days programme | Work in progress, 100 days progress | 17/01/2023 |
| 57 | 100DAYS/NH-02&NH-137A/2022-23 | Beautification of roads of National Highways along Greater Imphal Area by providing bituminous layer on unpaved portion. | PWD | Imphal-West | 100 days programme | Work in progress, 100 days progress | 17/01/2023 |
| 58 | KPI/pavement with interlocking blocks KPI/325 | construction of pavement with interlocking blocks at Kangpokpi District HQ impvt of approach road to DC Office, kangpokpi | PWD | Kangpokpi | phase-I | work in progress (95%) completed | 29/01/2026 |
| 59 | KPI/Interlocking block B.Ed college KPI/326A | construction of pavement with interlocking paver blocks Kangpokpi District HQ SH B.Ed college road Kangpokpi | PWD | Kangpokpi | phase-I | work in progress (95% work completed) | |
| 60 | KPI/Interlocking blocks from NH 2 to ADC /334 | construction of rigid pavement with interlocking blocks at Kangpokpi District HQ Rd SH Impvt of approach rd from NH 2 to ADC and ZEO office Kangpokpi | PWD | Kangpokpi | phase-I | work in progress (95% work completed) | |