Project Updates
Showing 161-180 of 30,450 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
161MSPCLC30Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV LILO line & related civil works at Paoyi, Ukhrul District.POWER (MSPCL)UkhrulX8519/03/2025
162MSPCLC6Installation of 2x5 MVA, 33/11 kV Sub-Station at MayangkhangPOWER (MSPCL)SenapatiX75%20/12/2017
163MSPCLC9Installation of 2x2.5 MVA 33/11 KV Sub-station along with the associated 33 KV line & related work at GelnelPOWER (MSPCL)KangpokpiX10005/10/2020
164MSPCLC45Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Akampat, Imphal East District on turn key POWER (MSPCL)Imphal-Eastx8211/12/2025
165MSPCLC9Installation of 2x2.5 MVA 33/11 KV Sub-station along with the associated 33 KV line & related work at GelnelPOWER (MSPCL)KangpokpiX100 percent Completed23/02/2018
166MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed21/01/2020
167MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100%
168MSPCLC46Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Liyaikhunou, Senapati DistrictPOWER (MSPCL)Senapatix8519/03/2025
169MSPCLC19Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at GumnomPOWER (MSPCL)UkhrulX65%17/11/2017
170MSPCLC29Installation of 2x2.25 MVA, 33 kV LILO line & related civil works at Thuyeng, Senapati District.POWER (MSPCL)Senapatix8511/12/2025
171MSPCLC21Installation of 2x5 MVA, 33/11 kV Sub-Station along with associated 33 kV LILO line & related works at Sekmai.POWER (MSPCL)Imphal-WestX10020/01/2020
172MSPCLC6Installation of 2x5 MVA, 33/11 kV Sub-Station at MayangkhangPOWER (MSPCL)SenapatiX100 %
173MSPCLC9Installation of 2x2.5 MVA 33/11 KV Sub-station along with the associated 33 KV line & related work at GelnelPOWER (MSPCL)KangpokpiX100 percent Completed23/02/2018
174MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
175MSPCLC5Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi KhullenPOWER (MSPCL)UkhrulX85%
176MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX8521/12/2019
177MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
178MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
179MSPCLC19Installation of 2x2.5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at GumnomPOWER (MSPCL)UkhrulX65%17/11/2017
180MSPCLC29Installation of 2x2.25 MVA, 33 kV LILO line & related civil works at Thuyeng, Senapati District.POWER (MSPCL)Senapatix8508/09/2025