#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
241MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
242MSPCLC5Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi KhullenPOWER (MSPCL)UkhrulX85%
243MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
244MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
245MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
246MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed21/01/2020
247MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
248MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed21/01/2020
249MSPCLC5Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi KhullenPOWER (MSPCL)UkhrulX85%
250MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%
251MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%21/03/2018
252MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
253MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
254MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
255MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
256MSPCLC1Installation of 2x5 MVA 33/11 KV Sub-station at Mao along with the associated 33 KV line & related work in Senapati District, ManipurPOWER (MSPCL)SenapatiX100% completed
257MSPCLC36Re-stringing & strengthening of 33 kV line from Yurembam to Leimakhong on turn-key basisPOWER (MSPCL)Imphal-WestX50%13/02/2020
258MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%21/03/2018
259MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%
260MSPCLB8Augmentation of Rengpang 132/33 kV SS by installing 132/33 kV Single Phase transformerPOWER (MSPCL)TamenglongX80%21/03/2018