Progress
 
 
Project Details
DAR-2024-000826
SHD/constn of Bank Building security bloc/183
COnstn of Bank building, Security personal block & staff qtr at Bungte chiru SD HQ
2023-11-21
PWD
Kangpokpi
120.00
70
State Plan
Completed
2023-2024
24.68257330069105,93.75921535491977
Bank Building, Security block, staff qtr
Progress Update : 2024-07-27
Completed
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6821374,93.7593422
0.050133223492224
Approved
2025-02-10 10:27:35
pwdse2ce
70
Bank building, security block, staff quarter

Progress Update : 2024-07-27
Completed
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6823902,93.7593093
0.022462705163886
Approved
70
Bank building, security block, staff quarter

Progress Update : 2024-07-27
completed
2023-2025
Sadarhills
24.68257330069105,93.75921535491977
24.6828303,93.7589766
0.037395478908509
Approved
70
bank building, security block, staff quarter

Progress Update : 2024-07-27
Completed
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6829495,93.7591604
0.042196362679383
Approved
70
Bank building, security block, staff quarter

Progress Update : 2024-07-27
in progress
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6826891,93.7592207
0.012886824818347
Approved
2024-07-30 08:36:07
pwdse2ce
0
bank building, security block, staff quarter

Progress Update : 2024-07-27
In progress
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6825419,93.7592374
0.0041422880414471
Approved
2024-07-30 08:36:49
pwdse2ce
0
Banking building, security personal block, staff quarter

Foundation & Inauguration
-
-
-

-
-
-