Progress
 
 
Project Details
DAR-2024-000694
SPT/Vaophea Junction to Kinafii colony/135
Impvt of road from Vaophea Junction to Kinafii colony via Rodziikhao
13/10/2023
PWD
Senapati
100.00
44.46
State Plan
completed
1
25.381937549503743,94.17776870727573
Hill c utting , GSB, Kutcha drain and 900 mm dia pipe culvert
Progress Update : 09/02/2025
completed
1
eesptd
25.381937549503743,94.17776870727573
25.3804771,94.1773991
0.16657754727957
44.46
hillcutting,culvert,gsb

Progress Update : 09/02/2025
completed
1
eesptd
25.381937549503743,94.17776870727573
25.3851392,94.1773201
0.35883122999538
44.46
hillcutting,culvert,gsb

Progress Update : 09/02/2025
completed
1
eesptd
25.381937549503743,94.17776870727573
25.3837739,94.1786319
0.22183282629731
44.46
hillcutting,culvert,gsb

Progress Update : 09/02/2025
completed
1
eesptd
25.381937549503743,94.17776870727573
25.3828092,94.1796762
0.21473509612188
44.46
hillcutting,culvert,gsb

Progress Update : 26/07/2024
In progress
1
eesptd
25.381937549503743,94.17776870727573
25.3775572,94.1750738
0.55723373360593
0
hillcutting,drain,culvert ,gsb

Progress Update : 26/07/2024
In progress
1
eesptd
25.381937549503743,94.17776870727573
25.3849065,94.1775172
0.33108175290975
0
hillcutting,drain,culvert ,gsb

Progress Update : 26/07/2024
In progress
1
eesptd
25.381937549503743,94.17776870727573
25.3849079,94.1774633
0.33169392266459
0
hillcutting,drain,culvert ,gsb

Progress Update : 26/07/2024
In progress
1
eesptd
25.381937549503743,94.17776870727573
25.3774067,94.1749256
0.57911387921838
0
hill cutting,drain,culvert,gsb

Progress Update : 19/07/2024
50% completed
1
eesptd
25.381937549503743,94.17776870727573
25.3851088,94.1776362
0.35286116486141
30
hillcutting,drain,gsb, pipe culvert