Progress
 
 
Project Details
DAR-2018-000216
WRD-FCW-76
Improvement of River bund along Imphal River RBB at Hayel, Bengun
2017-11-03
Water Resources Department (WRD)
Imphal-West
49.58
0.00
State Plan
Completed
Last phase
24.607138902422342,93.89902735339501
The project is implemented for improvement of Imphal River bund by providing earthwork at this location.
Progress Update : 2018-02-14
Completed
Last phase
FCD-1
24.607138902422342,93.89902735339501
24.60826951,93.89568536
0.3604771845728
Approved
2018-02-23 04:12:34
approverifcd
0
Earthwork Bangoo/hangoon 1

Foundation & Inauguration
-
-
-

-
-
-