DAR-2024-000670
UKL/Raisheo Jn to Phalee Ukhrul (Leftout)/111
Impvt of road from Raisheo Jn to Phalee, Ukhrul District (Leftout Portion) Phase -I-2km
20/11/2023
PWD
Ukhrul
120.00
0.00
State Plan
40% completed
Phase-I
25.14811,94.28357
Widening, Kutcha drain, shingling, WBM-I, Retaining wall
Progress Update : 18/10/2024
40% completed
Phase-I
eeukld
25.14811,94.28357
25.1368015,94.2817168
1.2711481662072
0
widening,GSB,WBM and retaining wall

Progress Update : 18/10/2024
40% completed
Phase-I
eeukld
25.14811,94.28357
25.1383135,94.2829896
1.090834143186
0
wideninh, GSB, WBM and Retaining wall

Progress Update : 18/10/2024
40% completed
Phase-
eeukld
25.14811,94.28357
25.1399573,94.2836417
0.90652399187462
0
widening,GSB,WBM and retaining wall

Progress Update : 18/10/2024
40% completed
Phase-I
eeukld
25.14811,94.28357
25.1421194,94.2833652
0.66641117290668
0
widening, GSB, WBM and Retaining wall

Progress Update : 18/10/2024
40% completed
Phase-I
eeukld
25.14811,94.28357
25.1434997,94.285428
0.54566456438726
0
widening, GSB, WBM and Retaining wall