Progress
 
 
Project Details
DAR-2024-000461
SS/23-D3/DuithanjangJHS(Dila)-NL
Construction of Dilapidated Building Upper Primary School for the year 2023-2024 at Duithanjang Junior High School, Noney, Manipur.
2023-08-29
Education (S)
Noney
72.54
50.39
CSS / CPS
completion
final
24.66476845654073,93.5226156754631
Construction of Dilapidated Building Upper Primary School for the year 2023-2024 at Duithanjang Junior High School, Noney, Manipur. 1 SH Construction of 3(three) Classroom. 2 SH Construction of Toilet for Boys & Girls. 3 SH Construction of Septic Tank & Soak Pit.
Progress Update : 2026-03-06
completion
final
so11.eew
24.66476845654073,93.5226156754631
24.6647667,93.5226983
0.008351206956861
Approved
2026-04-06 09:25:30
ee3@eew
0
front view with overhead tank

Progress Update : 2026-03-06
completion
final
so11.eew
24.66476845654073,93.5226156754631
24.66477,93.52268
0.006501888828429
Approved
2026-04-06 09:25:47
ee3@eew
0
Side view of classrooms

Progress Update : 2026-03-06
completed
Final
so11.eew
24.66476845654073,93.5226156754631
24.664865,93.52257
0.011684966513208
Approved
2026-04-06 09:26:14
ee3@eew
0
Inside view of classroom

Progress Update : 2026-03-06
completed
Final
so11.eew
24.66476845654073,93.5226156754631
24.6647367,93.5226383
0.004204906318485
Approved
2026-04-06 09:26:39
ee3@eew
0
Inside view of classroom

Progress Update : 2026-03-06
completed
Final
so11.eew
24.66476845654073,93.5226156754631
24.6647068,93.5225416
0.010150044140728
Approved
2026-04-06 09:27:22
ee3@eew
0
Inside view for Urinal block of school

Progress Update : 2026-03-06
completed
Final
so11.eew
24.66476845654073,93.5226156754631
24.6648467,93.522405
0.022996761292487
Approved
2026-04-06 09:29:12
ee3@eew
0
Inside view of toilet

Progress Update : 2026-03-06
completed
Final
so11.eew
24.66476845654073,93.5226156754631
24.6648567,93.522285
0.034823925250387
Approved
2026-04-06 09:28:44
ee3@eew
0
Front view of toilet block

Progress Update : 2026-03-06
completed
Finally
so11.eew
24.66476845654073,93.5226156754631
24.664815,93.52238
0.024369663382498
Approved
2026-04-06 09:28:17
ee3@eew
0
Side view of toilet and classrooms

Progress Update : 2024-05-17
in-progress (Roofing level )
first
so11.eew
24.66476845654073,93.5226156754631
24.6645217,93.5223117
0.041185060431969
Approved
2024-05-27 10:00:03
ee3@eew
0
Side View

Progress Update : 2024-05-17
in progress (Roofing level)
1st phase
so11.eew
24.66476845654073,93.5226156754631
24.664895,93.5225867
0.014371584586107
Approved
2024-05-27 09:59:43
ee3@eew
0
Front view

Foundation & Inauguration
-
-
-

-
-
-