Progress
 
 
Project Details
DAR-2024-000443
SS/D-IV/LAKHAMAI H/S/SPT
Strengthening of Govt Secondary & Hr Secondary under Samagra Shiksha, Manipur during 2022-2023 at Lakhamai H/S, Senapati, Manipur.
18/03/2023
Education (S)
Senapati
46.94
27.56
CSS / CPS
the work has been completed upto roofing
2022-2023
25.382387645597692,94.30686355620158
Strengthening of Govt Secondary & Hr Secondary under Samagra Shiksha, Manipur during 2022-2023 at Lakhamai H/S, Senapati, Manipur. sh construction of two staff quarter 2 construction of twon septic tank and soak pit
Progress Update : 08/08/2025
the work has been completed upto roofing
2022-2023
so9.eew
25.382387645597692,94.30686355620158
25.3824813,94.3064037
0.047354356369792
0
construction of 2 staff quarter ,font view

Progress Update : 08/08/2025
the work has been completed upto roofing
2022-2023
so9.eew
25.382387645597692,94.30686355620158
25.3821035,94.3063919
0.056948390606096
0
construction of two staff quarter

Progress Update : 08/08/2025
the work has been completed upto roofing
2022-2023
so9.eew
25.382387645597692,94.30686355620158
25.3823235,94.3065888
0.028507368036134
0
construction of two staff quarter front view

Progress Update : 12/04/2025
the work has been completed upto roofing
2022-23
so9.eew
25.382387645597692,94.30686355620158
25.3823363,94.306635
0.023658901703409
0
construction of two staff quarter

Progress Update : 27/06/2024
inprogress
First
so9.eew
25.382387645597692,94.30686355620158
25.3823664,94.3066135
0.025230509474897
0
back side veiw

Progress Update : 06/06/2024
in progress
First
so9.eew
25.382387645597692,94.30686355620158
25.4232913,94.3306669
5.1381621193917
0
Side view

Progress Update : 06/06/2024
in progress
first
so9.eew
25.382387645597692,94.30686355620158
25.4200333,94.3409396
5.4069622901491
0
Top view