Progress
 
 
Project Details
DAR-2024-000189
EE/BPR/Impvt Ningthoukhong Awang IVRS
Improvement of Ningthoukhong Awang IVRs (Portion-1) -4km (SH- Northern and Western portion)
09/11/2023
PWD
Bishnupur
150.00
53.76
State Plan
completed
phase 1
24.572489237507863,93.76811733829801
road work
Progress Update : 05/02/2026
completed
phase 1
lalit
24.572489237507863,93.76811733829801
24.5761801,93.764598
0.54319362376006
53.76
gsb wbm p.c etc.

Progress Update : 09/08/2024
100pc
phase 1
lalit
24.572489237507863,93.76811733829801
24.5758095,93.7681557
0.36919897541325
12
scarifying gsb wbm PC Culvert etc.