Progress
 
 
Project Details
DAR-2024-000060
SS/23-D3/TamlokPS(Dila)-NL
Construction of Dilapidated Building Upper Primary School under Samagra Shiksha (Elementary), Manipur during 2022-2023 at Tamlok Primary School, Noney
05/01/2023
Education (S)
Noney
73.04
51.13
CSS / CPS
Completed
final
24.812442357167637,93.53174862671129
Construction of Dilapidated Building Upper Primary School under Samagra Shiksha (Elementary), Manipur during 2022-2023 at Tamlok Primary School, Noney, Manipur. 1) SH. Construction of 5(five) Classrooms. 2) SH. Construction of Toilet for Boys & Girls.
Progress Update : 18/11/2025
Completed
final
so10.eew
24.812442357167637,93.53174862671129
24.8123583,93.5320267
0.029580178005821
0
Front view of classroom

Progress Update : 18/11/2025
Completed
final
so10.eew
24.812442357167637,93.53174862671129
24.8123583,93.5320266
0.029570579715472
0
Full front view

Progress Update : 18/10/2025
Completed
Final
so10.eew
24.812442357167637,93.53174862671129
24.8122333,93.531835
0.024825792715348
0
Inside view of Toilet

Progress Update : 18/10/2025
Completed
Final
so10.eew
24.812442357167637,93.53174862671129
24.8120917,93.53196
0.044444110561602
0
Inside view of Toilet

Progress Update : 18/10/2025
Completed
Final
so10.eew
24.812442357167637,93.53174862671129
24.81218,93.5317917
0.029493528166193
0
Front view of Toilet

Progress Update : 18/10/2025
Completed
Final
so10.eew
24.812442357167637,93.53174862671129
24.812225,93.5318183
0.025170073603893
0
Inside view of classroom

Progress Update : 24/01/2024
In progress
1st RA
so10.eew
24.812442357167637,93.53174862671129
24.8116279,93.4717688
6.0541769865661
0
Front view

Progress Update : 24/01/2024
In progress
1st RA
so10.eew
24.812442357167637,93.53174862671129
24.81364,93.53082
0.16283960511844
0
Side full view