Progress
 
 
Project Details
DAR-2024-000033
CB@NONEY2021
Construction of District Court Building at Noney
2021-04-05
Law & Legislative Affairs Department
Noney
1000.00
65000000
Manipur Tribal Development Corporation Ltd
State Plan
80%
1
24.856185,93.587811
District Court Building, R.C.C. Frame G+1 structure containing 3 Nos. Of Court Room with supporting staff room and supporting spaces.
Progress Update : 2025-07-08
80%
1
Mtdc_Law
24.856185,93.587811
24.8561301,93.5882241
0.042122188973392
Approved
2025-07-15 12:39:15
lawadmn
65000000
Construction of High Court at Noney District

Progress Update : 2024-07-26
53% completed
Phase- 1
Mtdc_Law
24.856185,93.587811
24.8562656,93.5880042
0.021453504992067
Approved
2024-08-14 08:00:10
lawadmn
450
construction of court Building at Noney

Progress Update : 2024-07-26
53% completed
Phase- 1
Mtdc_Law
24.856185,93.587811
24.8562656,93.5880042
0.021453504992067
Approved
2024-08-12 10:51:43
lawadmn
0
construction of court Building at Noney

Progress Update : 2024-07-26
53% completed
Phase- 1
Mtdc_Law
24.856185,93.587811
24.8562656,93.5880042
0.021453504992067
Approved
2024-08-12 10:52:10
lawadmn
0
construction of court Building at Noney

Progress Update : 2024-01-26
40% Completed
Phase -1
Mtdc_Law
24.856185,93.587811
24.86058,93.5907583
0.57203270117253
Approved
2024-02-02 10:30:52
lawadmn
0
On going construction of court in Noney

Progress Update : 2024-01-26
40% Completed
Phase -1
Mtdc_Law
24.856185,93.587811
24.8592715,93.5880715
0.3441914692245
Approved
2024-08-12 10:52:33
lawadmn
0
On going construction of court in Noney

Progress Update : 2024-01-26
40% Completed
Phase -1
Mtdc_Law
24.856185,93.587811
24.8592715,93.5880715
0.3441914692245
Approved
2024-08-12 10:52:55
lawadmn
0
On going construction of court in Noney

Foundation & Inauguration
-
-
-

-
-
-