Progress
 
 
Project Details
MSPCLC2
Installation of 2x5 MVA 33KV S/S along with the associated 33KV line and related civil works at Heirok Thokchom Leikai under IPDS
11/05/2016
POWER (MSPCL)
Thoubal
881.22
95.01
IPDS
On going
70 % completed
24.586708689059723,94.07204161999357
Construction of 2x5 MVA 33KV S/S along with the associated 33KV line and related civil works at Heirok Thokchom Leikai under IPDS for providing 24x7 power to area around Heirok Thokchom Leikai
Progress Update : 19/11/2017
On going
70 % completed
thoubal12
24.586708689059723,94.07204161999357
24.5786228,94.0781564
1.0911392073185
0
33/11KV Heirok SS, 2*5 MVA capacity

Progress Update : 19/11/2017
On going
70 % completed
thoubal12
24.586708689059723,94.07204161999357
24.585871770698,94.073139758907
0.14487060887916
0
33/11KV Heirok SS, 2*5 MVA capacity

Progress Update : 19/11/2017
On going
70 % completed
thoubal12
24.586708689059723,94.07204161999357
24.5786228,94.0781564
1.0911392073185
0
33/11KV Heirok SS, 2*5 MVA capacity

Progress Update : 24/04/2017
Ongoing
Phase2
roshano
24.586708689059723,94.07204161999357
24.5782526,94.0773269
1.0814887486478
0
Land Development - completed, Foundation- Transformer - 2/2 completed, Foundation gantry Tower - 10/10 completed, Erection of gantry tower - completed, Foundation Major Equipment - completed, Control Room Building - completed.

Progress Update : 24/04/2017
Ongoing
Phase2
roshano
24.586708689059723,94.07204161999357
24.5782526,94.0773269
1.0814887486478
0
Land Development - completed, Foundation- Transformer - 2/2 completed, Foundation gantry Tower - 10/10 completed, Erection of gantry tower - completed, Foundation Major Equipment - completed, Control Room Building - completed.

Progress Update : 24/04/2017
Ongoing
Phase2
roshano
24.586708689059723,94.07204161999357
24.5782526,94.0773269
1.0814887486478
0
Land Development - completed, Foundation- Transformer - 2/2 completed, Foundation gantry Tower - 10/10 completed, Erection of gantry tower - completed, Foundation Major Equipment - completed, Control Room Building - completed.

Progress Update : 24/04/2017
Ongoing
Phase2
roshano
24.586708689059723,94.07204161999357
24.5782526,94.0773269
1.0814887486478
0
Land Development - completed, Foundation- Transformer - 2/2 completed, Foundation gantry Tower - 10/10 completed, Erection of gantry tower - completed, Foundation Major Equipment - completed, Control Room Building - completed.

Progress Update : 24/04/2017
Ongoing
Phase2
roshano
24.586708689059723,94.07204161999357
24.5782526,94.0773269
1.0814887486478
0
Land Development - completed, Foundation- Transformer - 2/2 completed, Foundation gantry Tower - 10/10 completed, Erection of gantry tower - completed, Foundation Major Equipment - completed, Control Room Building - completed.