Progress
 
 
Project Details
Major Repairing
Major repairing of Tribal market complex New Lambulane, Imphal
2016-12-05
TA and Hills
Imphal-West
5000000.00
5000000
State Plan
Completed
final
24.8085998,93.948309
R.C.C.structure of Tribal Market Block - A ground and first floor damaged by the Earth quake occurred on the 4th January, 2016
Progress Update : 2017-06-21
Completed
final
tahmobileapp
24.8085998,93.948309
24.8076559,93.9480897
0.10726042564622
Approved
2017-06-21 14:19:12
tahapprover
5000000
R.C.C structure of Tribal Market Block - A ground and first floor damaged by the Earth-Quake occurred on the 4th January, 2016

Progress Update : 2017-06-21
Completed
Final
tahmobileapp
24.8085998,93.948309
24.8232289,93.9406202
1.8022130694936
Approved
2017-06-21 14:28:59
tahapprover
6750000
R.C.C structure of Schedule Tribe Boys hostel at Adimjati Complex Ground and First floor damaged by the Earth-Quake occurred on 4th January, 2016

Progress Update : 2017-06-21
Completed
Final
tahmobileapp
24.8085998,93.948309
24.8265261,93.9442179
2.0355307256994
Approved
2017-06-21 14:34:42
tahapprover
5900000
R.C.C Structure of Schedule Tribe Girls Hostel Ground and First floor damage by the Earth-Quake occurred on the 4th January, 2016

Progress Update : 2017-06-21
completed
Final
tahmobileapp
24.8085998,93.948309
24.7857354,93.9393577
2.6980655279019
Approved
2017-06-21 14:38:27
tahapprover
5000000
R.C.C. Structure of Schedule Tribe Boys Hostel at Langol, Imphal, Ground and First floor damage by the Earth-Quake occurred on the 4th January, 2016

Foundation & Inauguration
-
-
-

-
-
-