Progress
 
 
Project Details
DAR-2023-000641
SPT/DAR/2022-23/R2/320-16 Kodom Khullen
Impvt of road at Kodom Khullen and Kodom Khavii
23/02/2023
PWD
Senapati
60.00
0.00
State Plan
In progress
Phase I
25.354607,94.290878
Kutcha Drain, GSB, WBM PC & Pipe Culvert and Pipe Culvert
Progress Update : 30/03/2023
In progress
Phase I
eesptd
25.354607,94.290878
25.3546073,94.2908789
0.00013425232662458
0
WBM in progress

Progress Update : 30/03/2023
In progress
Phase I
eesptd
25.354607,94.290878
25.3529454,94.2844642
0.67041757525817
0
WBM in progress