Progress
 
 
Project Details
DAR-2023-000472
IED/Pungdongbam Lamkhai-Loushangkhong/829
Impvt. of road from Pungdongbam lamkhai to Loushangkhong Bridge
23/02/2023
PWD
Imphal-East
90.00
39
State Plan
completed
NA
24.87178914388115,94.04120538996581
Progress Update : 11/04/2025
completed
NA
yaiphabaIreng
24.87178914388115,94.04120538996581
24.8769687,94.0412036
0.57591268069631
39
upto blacktopping completed

Progress Update : 07/03/2025
80%
NA
thengra
24.87178914388115,94.04120538996581
24.8781511,94.0412032
0.70738324875258
39
pc topping

Progress Update : 25/06/2024
in progress
NA
thengra
24.87178914388115,94.04120538996581
24.877361,94.0408182
0.62076227486838
24
Impvt of Road - 60 pc completed - BT surface