Progress
 
 
Project Details
DAR-2023-000366
SDH/DAR/2022-23/R2/324-6 SDO Office Lhungtin
Improvement of approach road for the SDO Office, Lhungtin under Saikul A/C
23/02/2023
PWD
Kangpokpi
50.00
0.00
State Plan
On going
2022-23
25.0835278,94.12008333
E/W in banking, GSB, WBM, PC & Pipe Culvert
Progress Update : 26/03/2023
On going
2022-23
Sadarhills
25.0835278,94.12008333
25.084335,94.1198267
0.093398813917182
0
GSB

Progress Update : 26/03/2023
On going
2022-23
Sadarhills
25.0835278,94.12008333
25.084335,94.1198267
0.093398813917182
0
E/w in banking, GSB

Progress Update : 26/03/2023
On going
2022-23
Sadarhills
25.0835278,94.12008333
25.0843517,94.1198167
0.095462986458271
0
E/w in banking, GSB