Progress
 
 
Project Details
DAR-2022-001315
EE/BPR/Renov & Beautifcatin of DLO Office 3&4
Renovation & Beautification of DLO Office 3&4
24/12/2019
PWD
Bishnupur
100.00
35
State Plan
90pc
Phase 1
24.609676882843296,93.75718877116392
Renovation and Beautification
Progress Update : 20/03/2023
90pc
Phase 1
lalit
24.609676882843296,93.75718877116392
24.6096618,93.7572927
0.010639020426799
35
Plaster putty primer weather shield etc.

Progress Update : 16/11/2022
90 pc
Phase 1
lalit
24.609676882843296,93.75718877116392
24.6095813,93.7571883
0.010628002997186
35
Plaster dismantling, PLASTERING, PAINTING, ROOF TREATMENT, SANITARY ITEMS ITEMS ETC.

Progress Update : 16/11/2022
Ongoing
Phase 1
lalit
24.609676882843296,93.75718877116392
24.6095857,93.7572065
0.010295499232549
0
Plaster dismantling, PLASTERING, PAINTING, ROOF TREATMENT, SANITARY ITEMS ITEMS ETC.

Progress Update : 16/11/2022
Ongoing
Phase 1
lalit
24.609676882843296,93.75718877116392
24.6095792,93.7572076
0.011026685534601
0
Plaster dismantling, PLASTERING, PAINTING, ROOF TREATMENT, SANITARY ITEMS ITEMS ETC.

Progress Update : 16/11/2022
Ongoing
Phase 1
lalit
24.609676882843296,93.75718877116392
24.6096101,93.7572064
0.0076358776905678
0
Plaster dismantling, PLASTERING, PAINTING, ROOF TREATMENT, SANITARY ITEMS ITEMS ETC.