Progress
 
 
Project Details
DAR-2022-000997
MSPCLC53
Installation of 2x2.5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Nampisha, Kamjong District on turn key basis
18/12/2019
POWER (MSPCL)
Kamjong
1310.99
691.64
POWER (MSPCL)
Central Sector
81.5%
control room
24.7235622,94.4865568
Approved project cost post 1st amendment vide work order no. 4/4/NPSHA(KMJ)/33KVSS/2018-MSPCL(PURCH)/954-66 dated 20th May, 2026 is rs. 1310.99 (in lakhs)
Progress Update : 23/05/2026
81.5%
control room
red.jack
24.7235622,94.4865568
24.7095878,94.4925967
1.6692747412762
691.64
plastering of brick wall

Progress Update : 12/12/2025
79%
xx
mangangsana
24.7235622,94.4865568
24.709335,94.4926117
1.6960161882326
691.64
control room and switcheyard foundation work completed

Progress Update : 20/06/2025
70
1
mangangsana
24.7235622,94.4865568
24.7091527,94.4926671
1.7169415313605
581.53
Civil Works and Switchyard foundation work in progress

Progress Update : 28/02/2025
60%
x
mangangsana
24.7235622,94.4865568
24.9107847,94.1267885
41.852683751696
411.53
Materials at yangangpokpi site

Progress Update : 24/08/2022
40%
xyz
nongthom
24.7235622,94.4865568
24.8112615,93.9136671
58.656206207357
0
xyz