Progress
 
 
Project Details
DAR-2022-000872
Edn/D-2/Heirok HS- TBL
Implementation of School Fagathansi Mission-2nd Phase at Heirok High School, Heirok A/C, Thoubal, Manipur.
2021-11-08
Education (S)
Thoubal
71.79
52.50
Completed IEI
Nill
24.587260220388654,94.06139302253814
Implementation of School Fagathansi Mission-2nd Phase at Heirok High School, Heirok A/C, Thoubal, Manipur. ( Sh: Repairing Works) (Sh: Construction of 1(one) Classroom) (Sh: Construction of Girls Toilet Block & Sh: Construction of Girls Septic Tank)
Progress Update : 2024-09-18
Completed IEI
Nill
so7.eew
24.587260220388654,94.06139302253814
24.5852355,94.0652336
0.44885593504935
Approved
2024-09-25 08:19:45
ee2.eew-mn
0
interior View

Progress Update : 2024-09-18
Completed IEI
Nill
so7.eew
24.587260220388654,94.06139302253814
24.5875467,94.059045
0.23953071973506
Approved
2024-09-25 08:20:59
ee2.eew-mn
0
interior View

Progress Update : 2024-09-18
Completed IEI
Nill
so7.eew
24.587260220388654,94.06139302253814
24.5865791,94.0608166
0.09556271668861
Approved
2024-09-25 08:29:11
ee2.eew-mn
0
Electric fuse

Progress Update : 2024-09-05
Completed IEI
construction
so7.eew
24.587260220388654,94.06139302253814
24.5864986,94.061167
0.087713529257566
Approved
2024-09-25 08:23:14
ee2.eew-mn
0
Toilet Front

Progress Update : 2024-09-05
Completed IEI
Nill
so7.eew
24.587260220388654,94.06139302253814
24.5870915,94.0610474
0.039662418221536
Approved
2024-09-25 08:24:52
ee2.eew-mn
0
Interior Toilet

Progress Update : 2023-11-03
Completed
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.58738468,94.06116098
0.027238668905775
Approved
2023-11-16 09:07:04
ee2.eew-mn
0
Interior View (Toilet)

Progress Update : 2023-11-03
Completed
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.5873648,94.0613088
0.014412911117158
Approved
2023-11-16 09:07:58
ee2.eew-mn
0
Interior view

Progress Update : 2023-11-03
Completed
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.5870858,94.0615998
0.028516850158524
Approved
2023-11-16 09:12:50
ee2.eew-mn
0
Interior View (Classroom)

Progress Update : 2023-11-03
Completed
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.5869568,94.0614773
0.034796742414889
Approved
2023-11-16 09:13:37
ee2.eew-mn
0
Front View (Classroom)

Progress Update : 2023-11-03
Completed
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.5866781,94.0599816
0.1566987497366
Approved
2023-11-16 09:08:52
ee2.eew-mn
0
Front view (Toilet)

Progress Update : 2023-11-03
Completed
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.58704251,94.06149118
0.026162675110767
Approved
2023-11-16 09:14:27
ee2.eew-mn
0
Rear View (Classroom)

Progress Update : 2022-07-23
Under Repairing
nill
so7.eew
24.587260220388654,94.06139302253814
24.5870701,94.0612147
0.027784069589486
Approved
2022-08-24 05:48:31
ee2.eew-mn
0
Stair View

Progress Update : 2022-07-23
Under Repairing
nill
so7.eew
24.587260220388654,94.06139302253814
24.5871034,94.0612156
0.025016904337524
Approved
2022-08-24 05:49:36
ee2.eew-mn
0
Interior View

Progress Update : 2022-07-23
Under Repairing
nill
so7.eew
24.587260220388654,94.06139302253814
24.5873527,94.0615307
0.017306317404767
Approved
2022-08-24 05:51:17
ee2.eew-mn
0
Front View

Progress Update : 2022-07-20
Under Repairing
Nil
so2.eew-mn
24.587260220388654,94.06139302253814
24.5882855,94.0620399
0.13142983940778
Approved
2022-08-24 05:52:21
ee2.eew-mn
0
Back View

Foundation & Inauguration
-
-
-

-
-
-