Progress
 
 
Project Details
DAR-2022-000684
MSPDCL-STATEPLAN-096
Supply, Installation, Testing and commissioning of 13 nos of 20 mtr. High Mast lighting along with 300 watt of Led integral flood light
24/12/2021
POWER (MSPDCL)
ALL MANIPUR
100.37
0.00
State Plan
Ongoing
Ongoing
24.799611,93.935895
Supply, Installation, Testing and commissioning of 13 nos of 20 mtr. High Mast lighting along with 300 watt of Led integral flood light on turnkey Basis MS Industrial Systems LLP
Progress Update : 15/06/2022
Ongoing
Ongoing
Rajesh
24.799611,93.935895
24.79982435,93.93595354
0.024447013229544
0
High mast