Progress
 
 
Project Details
DAR-2022-000278
JNIMS/RSD-ATC
Constn of road side drain along New ATC Building and Raising of road level in front of New OPD Block for JNIMS,Porompat.
07/03/2020
PWD
Imphal-East
31.15
0.00
State Plan
In progress
Phase1
24.811418320108853,93.96213238175353
Road side drain, road works,etc.
Progress Update : 03/04/2022
In progress
Phase1
kmanitombi1
24.811418320108853,93.96213238175353
24.8119632,93.9623807
0.065563880015509
0
Road and drain work

Progress Update : 03/04/2022
In progress
Phase1
kmanitombi1
24.811418320108853,93.96213238175353
24.8119427,93.9623781
0.063360413641449
0
Road and drain work

Progress Update : 03/04/2022
In progress
Phase1
kmanitombi1
24.811418320108853,93.96213238175353
24.8121901,93.9625238
0.094470100795481
0
Road and drain work